ASX ANNOUNCEMENT
31 July 2023
JUNE QUARTERLY ACTIVITIES REPORT
Delta Lithium Limited (ASX: DLI) (“Delta” or the “Company”) is pleased to provide the following report on
activities undertaken during the June quarter, 2023.
June Quarter Highlights
•
Completed Idemitsu Australia $46.4M Strategic Investment Agreement.
•
Record metres drilled in the June quarter, comprising 82,589 metres completed (45,342m at Mt Ida,
37,247m at Yinnetharra). 8,894 samples currently with lab. Better drill results during the quarter
include;
o
o
Mt Ida Lithium Project
90.1m @ 0.95% Li2O from 650.8m in IDRD229W1
44.5m @ 1.2% Li2O from 357.3m in IDRD178
34.9m @ 1.3% Li2O from 398.3m in IDRD077
27.2m @ 1.2% Li2O from 430.4m in IDRD077W1
Yinnetharra Lithium project
43m @ 1.22% Li2O from 66m in YNRD082
20m @ 1.29% Li2O from 28m in YRRD011
33m @ 1.9% Li2O from 218m in YRRD118
19m @ 1.6% Li2O from 190m in YRRD114
29m @ 1.5% Li2O from 205m in YRRD120
•
Continued progress approval to commence mining at the Mt Ida Lithium Project expected in the 2H
CY2023.
•
Drilling results at Yinnetharra has now confirmed multiple mineralised pegmatites with commercial
scale opportunity and strikes exceeding 1600 metres length.
•
The company continues to recruit key people with extensive mine building and lithium experience
to the team.
•
Completed cooperation agreement with Mid West Ports in relation to supporting shipments out of
Geraldton from 2H 2024.
Commenting on the June quarter, Chairman of Delta Lithium, David Flanagan said:
“The highlights tell the story. We are one of the most active explorers in the country right now. We are
permitting a mine, building a terrific team, doing great deals and we are just getting started”
“Yinnetharra continues to deliver over and over and Mt Ida is on track to be Australia’s next lithium mining
operation. There is going to be plenty of newsflow in the second half of 2023.
“Securing the support of Idemitsu Australia via a $46.4m placement. It is one of the largest ever investments
by a traditional energy company in a critical minerals company. We are very pleased to have them on
board and we see this as further support for the quality of the management team and our assets.”
1
ASX ANNOUNCEMENT
31 July 2023
MT IDA LITHIUM PROJECT
Exploration and Resource Development
Following the release of the Company’s initial 12.7Mt @ 1.2% Li2O resource at Mt Ida, on 19 October 2022.
the Company continues working to fast track development of this resource base to deliver value for
shareholders. The company has resolved to pursue a speed to market strategy which specifically engages
a small team to run all possible work packages in parallel. It requires a higher intensity workload but it
presents the best opportunity to access highest commodity prices, manage execution and commisioning
risk and provide the best returns for shareholders.
During the quarter a total of 180 holes were drilled for a total of 45,342 metres (Diamond Drilling “DD” and
Revere Circulation “RC”), with the primary purpose of:
•
•
•
•
•
Geotechnical drilling with the aim of providing geotechnical parameters for mine design work
associated with the Mt Ida Early Works and DSO;
Completion of drilling the shallow portions of the Sister Sam and Timoni ore bodies to assist with the
completion of studies of a DSO operation;
Step out exploration drilling around Sister Sam, Timoni and the gap between Timoni and Sparrow;
Metallurgical drilling; and
Infill drilling to increase the categorisation of inferred to indicated.
In addition, the Company has a number of priority Air Core (“AC”) targets. AC drilling was completed as
initial follow up on regional soil sampling in 2022. This drilling was broad spaced but still detected four low
tenor anomalism (60-240ppm Li), typically found in the preferred greenstone host rocks within 100 metres of
mineralised pegmatites (Figure 1). These near surface targets are in the same prospective stratigraphic
location as the existing resources at Mt Ida and are currently being tested by RC drilling
During the June quarter, further encouraging assays were received pertaining to infill and extension drilling
around existing resources. These were announced on 13 April 2023:
o
44.5m @ 1.2% Li2O from 357.3m in IDRD178
o
90.1m @ 0.95% Li2O from 650.8m in IDRD229W1
o
27.2m @ 1.2% Li2O from 430.4m in IDRD077W1
o
34.9 @ 1.3% Li2O from 398.3m in IDRD077
o
14.1m @ 1.2% Li2O from 93.9m in IDRD145
o
11.7m @ 1.3% Li2O from 75.3m in IDRD197
o
6.8m @ 1.7% Li2O from 111.2m in IDRD149
o
5m @ 1.12% Li2O from 35m in TIRD024
o
6m @ 1.8% Li2O from 78.4m in IDRD195
o
41.2m @ 1.8% Li2O from 276.8m in IDRD162
o
26.2m @ 1.41% Li2O from 232.4m in IDRD128
o
24.1m @ 1.8% Li2O from 488.2m in IDRD141
o
14m @ 1.4% Li2O from 78m in SSRD046
The Company continues to advance infill, extension and exploration RC and DD drilling programs across the
Mt Ida Lithium Project. More than 4,783 Mt Ida samples are currently with the labs undergoing analysis with
results expected to arrive in batches over the next 6-12 weeks. The planned drill programs will cover more
than 200 holes and 60,000m through the balance of 2023.
2
ASX ANNOUNCEMENT
31 July 2023
Figure 1: Plan showing location of exploration with pending results
Mt Ida Lithium Concentrate Project
The Company’s key objective for Mt Ida is to export lithium concentrates as soon as possible. As previously
communicated, the Company has recognised that alongside the development pathway to a Concentrate
Project, an excellent opportunity exists to commence early works and and create an opportunity for the
export of a Direct Shipping Ore (“DSO”) product. The benefit of two (2) granted mining leases in combination
with the shorter development timeline of a DSO lithium project strongly supports an accelerated path to
production.
In executing early works and a DSO Project, a number of work packages that are also required for the
Concentrate Project can be completed ahead of time. Incremental capital investment and a phased
development approach that establishes a supply chain for DSO from mine to market, ahead of Concentrate
Project FID (Final Investment Decision), provides a significant opportunity to de-risk and accelerate
execution of the Concentrate Project. Multiple work streams are being progressed to enable
commencement of mining by December 2023, all of which will benefit the longer-term Mt Ida Lithium
Concentrate Project (the Concentrate Project).
3
ASX ANNOUNCEMENT
31 July 2023
June quarter progress:
•
Native Vegetation Clearing Permit (NVCP) for DSO mining has been approved following a public
consultation period. Mining Proposal for DSO mining still under assessment.
•
Mt Ida Road Diversion;
o
Advertised for public comment by Shire of Menzies on the 6 April, no objections received
o
Request to Department of Planning, Lands and Heriage (DPLH) submitted by Shire of Menzies;
request is for closure of part of Mt Ida Road and to dedicate the required bypass road as
road reserve
o
NVCP for the proposed road diversion submitted and currently under assessment
o
WML awarded the design work for new road alignment. On schedule to complete the 80%
design in August, which will be used for submission to Shire of Menzies.
•
Mt Ida Stage 1 Accommodation Village – General layout and quotes received for a 60 room Stage
1 accommodation village, which will support option for DSO production and be exapandable for
the Concentrate Project
•
Hydrogeology – First stage of water exploration program has been completed, with 3 production
bores constructed that will support DSO operations and a future Concentrate Project. Once pump
testing is complete and water flow rates are confirmed, the additional water requirement for
concentrate production can be established and a second stage water exploration program can
be initiated.
•
Mine planning work has continued for both the DSO initiative and the concentrate project. In
particular for the concentrate project this mine planning work is being used to guide site general
layouts for both DSO and Concentrate Project, infill drilling, and planning for a more significant
metallurgical testwork program
•
Port – Cooperation Agreement signed with Midwest Port Authority; the cooperation agreement
accommodates the export of both DSO and concentrate products.
•
Figure 2: Regional map showing Mt Ida in relation to major infrastructure.
4
ASX ANNOUNCEMENT
31 July 2023
Post quarter end:
•
Road Diversion – Access Agremeent agreed with Aurenne Group; along with Letter of Consent
supporting road diversion
•
James Howard to join the team and offer project management and support through MineBuild
Global. James is an experienced mining engineer with over 25 years of industry expertise in project
development and mine operations. His role will involve managing various packages pertaining to
the Concentrate Project and offering support to advance early works related to the DSO project.
YINNETHARRA LITHIUM PROJECT
The Yinnetharra Lithium Project covers a very large area of 575km2 in a newly emerging Lithium district within
the Gascoyne region of Western Australia. Yinnetharra is important to the Company’s long-term plans of
being a significant lithium concentrate producer. Geologists have identified lithium mineralisation with a
surface expression spread across several square kilometres. In addition, drilling has confirmed lithium bearing
pegmatites from surface to depths greater than 350 metres. Six well defined mineralised pegmatites have
now been defined at the Malinda target. Malinda now boasts a ‘Lithium Mile’ comprising two major parallel
ore zones M1 and M36 each now drilled out over 1.6km in strike length, remaining open down plunge.
Presenting as a large target and comparable to other areas of global scale endowments of lithium in
Western Australia, the Company has resolved to complete more than 400 drill holes, 90,000 metres at the
project in 2023.
The Yinnetharra Project includes the Malinda Prospect, currently being explored, and the newly found
Jamesons Prospect (Figure 3). Beyond these two prospects, there remain many other pegmatite targets yet
to be explored across the total tenement package.
Figure 3: Yinnetharra plan showing general location of drilling at the Malinda Prospect, newly discovered Jamesons
Prospect and the newly applied for tenement.
5
ASX ANNOUNCEMENT
31 July 2023
During the June quarter a total of 156 holes were drilled at the Malinda Prospect for 37,246 metres, with
highlights from initial assays including:
•
New drilling results include:
o
43m @ 1.22% Li2O from 66m in YRRD082
•
•
Inc 6m @ 3.3% Li2O from 88m
o
37m @ 0.9% Li2O from 92m in YRRD053
o
20m @ 1% Li2O from 164 m in YRRD055
New drilling results, all from M36 include:
o
29m @ 1.0% Li2O from 199m in YRRD133
o
9m @ 1.3% Li2O from 279m in YRRD132
o
33m @ 1.9% Li2O from 218m in YRRD118
o
19m @ 1.6% Li2O from 190m in YRRD114
Subsequent to the end of the quarter the Company reported;
o
29m @ 1.5% Li2O from 203m Inc. 11m @ 3% Li2O from 221m in YRRD120
o
36m @ 1.1% Li2O from 254m Inc. 6m @ 3.1% Li2O from 282m in YRRD095
o
30m @ 1.1% Li2O from 291m Inc. 10m @ 2.2% Li2O from 310m in YRRD071
The Company continues to progress diamond drilling as well as infill and expansion RC drilling programs
across the Project. More than 50 Lithium pegmatites have been identified at the Malinda Prospect and will
be progressively tested during the year.
Figure 4: Drill cross section at Yinnetharra.
6
ASX ANNOUNCEMENT
31 July 2023
As at the date of reporting there are 4,111 Yinnetharra samples with the laboratory pending analysis.
Heritage surveys have been completed during the June quarter with both the Yinggarda and Yamati Wajarri
Native Title groups.
Figure 5: Plan showing drilling at the Malinda Prospect.
CORPORATE
Capital
On 14 June 2023, the Company completed a $46.4 million strategic placement to Idemitsu Australia, issuing
65,636,000 new fully paid ordinary shares in the Company at an issue price of $0.7075 per share. The
placement was conducted at a 7.5% premium to the 10 day VWAP and an 8.0% premium to the most recent
closing price. https://www.investi.com.au/api/announcements/dli/42c383f5-cef.pdf
Proceeds raised from the Strategic Placement will be used for the following purposes:
• the progression of exploration and resource drilling at the Yinnetharra Lithium Project;
• camp upgrades and road diversions at the Mt Ida Lithium Project;
• feasibility studies at the Yinnetharra Lithium Project and the Mt Ida Lithium Project;
• 'early works' capital and development costs associated with potential direct shipping ore and future
lithium concentrates operations at the Mt Ida Lithium Project; and
• any other activity deemed appropriate by the Board as consistent with the Company's existing
strategy.
7
ASX ANNOUNCEMENT
31 July 2023
During the quarter, $2,457,500.50 was received for the exercise of 9,830,002 unlisted $0.25 options in the June
quarter. A further 84,583.25 was received for the exercise of 338,333 options that were converted to shares
post the end of the quarter.
There were 3,250,000 performance rights issued and 1,250,000 performance rights cancelled.
As at 30June 2023, Delta Lithium has the following securities on issue:
• 520,573,492 fully paid ordinary shares;
• 39,024,655 unlisted options (various exercise prices and expiry dates) and
• 30,740,000 performance rights (various vesting conditions and expiry dates).
Other
On 12 June 2023, the Company appointed Peter Gilford as Chief Financial Officer and Company Secretary
following the departure of Daniel Kendall. Peter is an experienced finance professional and brings a depth
of mining operational experience to the finance function.
Lithium marketing and business development
During the quarter the Company continued to engage with potential offtake partners and the broader
global lithium supply chain. This included meetings in Perth and on site with interested parties from a wide
variety of downstream lithium markets as well as offshore plant visits with significant groups in China coupled
with participation at leading industry conferences.
Spot prices for both lithium raw materials and lithium chemicals recovered during the quarter and remain
some 70% above prices observed at the beginning of 2022. The industry remains in a a pricing environment
that continues to see historically high long-term contract prices being realised by existing producers in
Australia, Chile and Argentina.
It is expected that average realised prices for 2023 under long-term contracts by both lithium concentrate
and lithium chemical producers in the lithium supply chain will be well above those acheived in calendar
2022. We continue to highlight that the vast majority of lithium raw material and chemical trade is under
long-term contracts and not via the thinly-traded spot market.
Downstream demand from the key electric vehicle sector continues to grow, with global electric vehicle
sales typcally stronger in the second half of the calendar year. The range of models being offered to an
eager consumer market continues to grow. Governments globally have enacted initiatives that encourage
electric vehicle uptake and showroom traffic here in Australia is at unprecedented levels.
The quarter has also seen additional capital investment and activity amongst global participants in the
automotive & battery manufacturing, lithium chemicals and mining sectors including:
•
•
•
•
•
•
Idemitsu investment into Delta Lithium, marking the first investment into hard rock lithium by a
significant global participant in the traditional energy sector.
Allkem/Livent merger delivering a top 5 lithium chemicals producer
Zhejiang Huayou Cobalt commencing production at their Arcadia lithium mine in Zimbabwe
Imerys announcement to build a 20,000 tpa lithium carbonate project with British Lithium
Posco announced plans to produce lithium hydroxide in South Korea from a new 25,000 tpa plant in
Youlchon. Production scheduled from 2025 and expansion to 100,000 tpa by 2028. Initial investment
is circa US$441m.
Livista Energy announced plans to build 40,000tpa lithium hydroxide plant in Lower Saxony, Germany
by 2026, with the potential to eventually double capacity. They have partnered with Technip
Energies on plant design.
8
ASX ANNOUNCEMENT
31 July 2023
ASX Compliance
For the purpose of Listing Rule 5.3.2, the Company confirms that there were no mining production and
development activities during the quarter by the Company or its subsidiaries.
In accordance with section 6 of the Appendix 5B, the Company advises that $141k was paid to related
parties of the entity and their associates during the quarter, including Executive and Non-Executive Director
fees.
Summary Mt Ida Mineral Resource Estimate as announced 19 October 2022
Li2O
Ta2O5
Tonnes
Grade
Li2O
Grade
(Mt)
(% Li2O)
(Kt)
(Ta2O5 ppm)
Total Indicated
3.3
1.4
46
246
Total Inferred
9.3
1.1
102
193
Total
12.7
1.2
148
207
Resource category
Table 1: Maiden Mineral Resource Estimate for Mt Ida Lithium Project.
9
ASX ANNOUNCEMENT
31 July 2023
Appendix 1 – Tenement Listing
Project
Location
Eureka
Western Australia
Eureka
Western Australia
Eureka
Western Australia
Eureka
Western Australia
Eureka
Western Australia
Eureka
Western Australia
Eureka
Western Australia
Eureka
Western Australia
Lockeridge
Western Australia
Mt Ida
Western Australia
Mt Ida
Western Australia
Mt Ida
Western Australia
Mt Ida
Western Australia
Mt Ida
Western Australia
Mt Ida
Western Australia
Mt Ida
Western Australia
Mt Ida
Western Australia
Mt Ida
Western Australia
Mt Ida
Western Australia
Mt Ida
Western Australia
Mt Ida
Western Australia
Mt Ida
Western Australia
Mt Ida
Western Australia
Mt Ida
Western Australia
Mt Ida
Western Australia
Mt Ida
Western Australia
Mt Ida
Western Australia
Mt Ida
Western Australia
Mt Ida
Western Australia
Mt Ida
Western Australia
Mt Ida
Western Australia
Mt Ida
Western Australia
Mt Ida
Western Australia
Mt Ida
Western Australia
Mt Ida
Western Australia
Mt Ida
Western Australia
Mt Ida
Western Australia
Mt Ida
Western Australia
Mt Ida
Western Australia
Mt Ida
Western Australia
Yinnetharra
Western Australia
Yinnetharra
Western Australia
Yinnetharra
Western Australia
Yinnetharra
Western Australia
Yinnetharra
Western Australia
Yinnetharra
Western Australia
Yinnetharra
Western Australia
Yinnetharra
Western Australia
Yinnetharra
Western Australia
Yinnetharra
Western Australia
Yinnetharra
Western Australia
Yinnetharra
Western Australia
*Application remains in ballot
Tenement
Status
L24/0234
M24/0189
M24/0584
M24/0585
M24/0586
P24/5116
P24/5548
P24/5549
E69/3871
E29/0640
E29/0771
E29/0895
E29/0944
E29/0964
M29/0002
M29/0094
M29/0165
M29/0422
M29/0429
M29/0444
P29/2394
P29/2397
P29/2398
P29/2399
P29/2400
P29/2401
P29/2402
P29/2403
P29/2404
P29/2405
P29/2406
P29/2407
P29/2487
P29/2529
P29/2666
P29/2667
P29/2668
P29/2669
L29/0166
L29/0171
E09/2169
E09/2170
E09/2283
E09/2545
E09/2544
E09/2621
E09/2705
E09/2716
E09/2772
E09/2806*
E09/2808*
E09/2814
Granted
Granted
Granted
Granted
Granted
Granted
Granted
Granted
Granted
Granted
Granted
Granted
Granted
Granted
Granted
Granted
Granted
Granted
Granted
Apllication
Granted
Granted
Granted
Granted
Granted
Granted
Granted
Granted
Granted
Granted
Granted
Granted
Granted
Granted
Granted
Granted
Granted
Granted
Granted
Granted
Granted
Granted
Granted
Granted
Surrendered
Application
Application
Application
Application
Application
Application
Application
Interest at start
of Quarter
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
0%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
Interest at end
of Quarter
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
0%
100%
100%
100%
100%
100%
100%
100%
10
ASX ANNOUNCEMENT
31 July 2023
This release is authorised by the Board of Delta Lithium Limited.
For further information, please contact:
Delta Lithium
David Flanagan, Chairman
+61 8 6109 0104
info@deltalithium.com.au
Investor/Media Enquiries
Citadel-MAGNUS
Michael Weir +61 402 347 032
Jono van Hazel +61 411 564 969
About Delta Lithium
Delta Lithium (ASX: DLI) is an exploration and development company focused on bringing high-quality,
lithium-bearing pegmatite deposits, located in Western Australia, into production. With a strong balance
sheet and an experienced team driving the exploration and development workstreams, Delta Lithium is
rapidly advancing its Mt Ida Lithium Project towards production. The Mt Ida Lithium Project holds a critical
advantage over other lithium developers with existing Mining Leases in place. To capitalise on the prevailing
buoyant lithium market, Delta Lithium is pursuing a rapid development pathway to unlock maximum value
for shareholders.
Delta Lithium also holds the highly prospective Yinnetharra Lithium Project that is already showing signs of
becoming one of Australia’s most exciting lithium regions. The Company is currently undergoing an
extensive 400 drill hole campaign to be completed throughout 2023.
Disclaimer & Competent Person Statements
This release may include forward-looking and aspirational statements. These statements are based on Delta
Lithium management’s expectations and beliefs concerning future events as of the time of the release of
this announcement. Forward-looking and aspirational statements are necessarily subject to risks,
uncertainties, and other factors, some of which are outside the control of Delta Lithium, that could cause
actual results to differ materially from such statements. Delta Lithium makes no undertaking to subsequently
update or revise the forward looking or aspirational statements made in this release to reflect events or
circumstances after the date of this release, except as required by applicable laws and the ASX Listing Rules.
Information in this Announcement that relates to exploration results is based upon work undertaken by Mr.
Charles Hughes, a Competent Person who is a Member of the Australasian Institute of Mining and Metallurgy
(AUSIMM). Mr. Hughes has sufficient experience that is relevant to the style of mineralisation and type of
deposit under consideration and to the activity which he is undertaking to qualify as a ‘Competent Person’
as defined in the 2012 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral
Resources and Ore Reserves’ (JORC Code). Mr. Hughes is an employee of Delta Lithium Limited and
consents to the inclusion in this announcement of the matters based on his information in the form and
context in which it appears. Refer to www.deltalithium.com.au for past ASX announcements.
Past Exploration results and Mineral Resource Estimates reported in this announcement have been previously
prepared and disclosed by Delta Lithium in accordance with JORC 2012. The Company confirms that it is
not aware of any new information or data that materially affects the information included in these market
announcements. The Company confirms that the form and content in which the Competent Person's
findings are presented here have not been materially modified from the original market announcement,
and all material assumptions and technical parameters underpinning Mineral Resource Estimates in the
relevant market announcement continue to apply and have not materially changed. Refer to
www.deltalithium.com.au for details on past exploration results and Mineral Resource Estimates.
11
Rule 5.5
Appendix 5B
Mining exploration entity and oil and gas exploration entity
quarterly cash flow report
Name of entity
DELTA LITHIUM LIMITED (ASX CODE: DLI)
ABN
Quarter ended (“current quarter”)
67 107 244 039
30 JUNE 2023
Current quarter
$A’000
Year to date
-
50
-
-
(b) development
-
-
(c)
production
-
-
(d) staff costs
(543)
(1,378)
(1,574)
(4,428)
-
-
Consolidated statement of cash flows
1.
Cash flows from operating activities
1.1
Receipts from customers
1.2
Payments for
(a)
(e)
exploration & evaluation (if expensed)
administration and corporate costs
(12 months)
$A’000
1.3
Dividends received (see note 3)
1.4
Interest received
623
1,186
1.5
Interest and other costs of finance paid
(1)
(7)
1.6
Income taxes paid
-
-
1.7
Government grants and tax incentives
21
221
1.8
Other (provide details if material)
-
-
1.9
Net cash from / (used in) operating activities
(1,474)
(4,356)
2.
Cash flows from investing activities
2.1
Payments to acquire:
-
2,009
-
(125)
(33)
(175)
(a)
entities (net of cash acquired)
(b) tenements
(c)
property, plant and equipment
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
P a g e |1
Consolidated statement of cash flows
(d) exploration & evaluation (if capitalised)
Current quarter
$A’000
Year to date
(13,669)
(35,919)
(12 months)
$A’000
(e)
investments
-
-
(f)
other non-current assets
-
-
entities
-
-
(b) tenements
-
-
(c)
-
35
(d) investments
-
-
(e)
other non-current assets
-
-
2.3
Cash flows from loans to other entities
-
-
2.4
Dividends received (see note 3)
-
-
2.5
Other (provide details if material)
-
-
2.6
Net cash from / (used in) investing activities
(13,701)
(34,175)
3.
Cash flows from financing activities
3.1
Proceeds from issues of equity securities
(excluding convertible debt securities)
46,437
101,682
3.2
Proceeds from issue of convertible notes
-
-
3.3
Proceeds from exercise of options
2,542
2,828
3.4
Transaction costs related to issues of equity
securities or convertible debt securities
(1,428)
(4,941)
2.2
Proceeds from the disposal of:
(a)
property, plant and equipment
3.5
Proceeds from borrowings
-
-
3.6
Repayment of borrowings
-
-
3.7
Transaction costs related to loans and
borrowings
-
-
3.8
Dividends paid
-
-
3.9
Principle payments of lease liability
(16)
(86)
3.10
Net cash from / (used in) financing activities
47,535
99,483
4.
Net increase / (decrease) in cash and cash
equivalents for the period
4.1
Cash and cash equivalents at beginning of
period
51,953
23,360
4.2
Net cash from / (used in) operating activities
(item 1.9 above)
(1,474)
(4,356)
4.3
Net cash from / (used in) investing activities
(item 2.6 above)
(13,701)
(34,175)
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
P a g e |2
Consolidated statement of cash flows
4.4
Net cash from / (used in) financing activities
(item 3.10 above)
4.5
Effect of movement in exchange rates on cash
held
4.6
Cash and cash equivalents at end of period
5.
Reconciliation of cash and cash
equivalents
Current quarter
$A’000
Year to date
47,535
99,483
-
-
84,312
84,313
Current quarter
$A’000
Previous quarter
$A’000
(12 months)
$A’000
at the end of the quarter (as shown in the
consolidated statement of cash flows) to the
related items in the accounts
5.1
Bank balances
69,149
11,839
5.2
Call deposits
15,163
40,114
5.3
Bank overdrafts
-
-
5.4
Other (provide details)
-
-
5.5
Cash and cash equivalents at end of quarter
(should equal item 4.6 above)
84,312
51,953
6.
Payments to directors of the entity and their associates
6.1
Aggregate amount of payments to related parties and their associates
included in item 1
97
6.2
Aggregate amount of payments to related parties and their associates
included in item 2
44
Current quarter
$A'000
Note: if any amounts are shown in items 6.1 or 6.2, your quarterly activity report must include a description of,
and an explanation for, such payments
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
P a g e |3
7.
Financing facilities available
Note: the term “facility’ includes all forms of financing
arrangements available to the entity.
Total facility amount at
quarter end
$A’000
Amount drawn at
quarter end
$A’000
Add notes as necessary for an understanding of the sources
of finance available to the entity.
7.1
Loan facilities
-
-
7.2
Credit standby arrangements
-
-
7.3
Other (Convertible loan)
-
-
7.4
Total financial facilities
-
-
7.5
Unused financial facilities available at quarter end
7.6
Include in the box below a description of each facility above, including the lender, interest rate,
maturity date and whether it is secured or unsecured. If any additional financing facilities have been
entered into or are proposed to be entered into after quarter end, include a note providing details
of those facilities as well.
-
NIL
8.
Estimated cash available for future operating activities
$A’000
8.1
Net cash from / (used in) operating activities (Item 1.9)
(1,474)
8.2
(Payments for exploration & evaluation classified as investing activities)
(item 2.1(d))
(13,669)
8.3
Total relevant outgoings (Item 8.1 + Item 8.2)
(15,143)
8.4
Cash and cash equivalents at quarter end (Item 4.6)
84,312
8.5
Unused finance facilities available at quarter end (Item 7.5)
8.6
Total available funding (Item 8.4 + Item 8.5)
8.7
Estimated quarters of funding available (Item 8.6 divided by Item 8.3)
84,312
5.57
Note: if the entity has reported positive relevant outgoings (ie a net cash inflow) in item 8.3, answer item 8.7 as
“N/A”. Otherwise, a figure for the estimated quarters of funding available must be included in item 8.7.
8.8
If Item 8.7 is less than 2 quarters, please provide answers to the following questions:
1.
Does the entity expect that it will continue to have the current level of net op
Share your feedback
Discover