ASX ANNOUNCEMENT
23 January 2024
DECEMBER QUARTERLY ACTIVITIES REPORT
Delta Lithium Limited (ASX: DLI) (“Delta” or the “Company”) is pleased to provide the following report on
activities undertaken during the December Quarter, 2023.
December Quarter Highlights
•
A maiden Mineral Resource Estimate (MRE) at the Yinnetharra Lithium Project was announced1:
o
combined Inferred and Indicated MRE of 25.7Mt @ 1.0% Li2O (at a 0.5% Li2O cut off),
o
26% of the MRE in higher confidence Indicated category: 6.7Mt @ 1.0% Li2O,
•
This MRE has been defined from only the Malinda prospect, which is the only prospect to have been
drilled to date at Yinnetharra.
•
The Mt Ida Lithium Project received approval from DEMIRS for the Mining Proposal and Mine
Closure Plan for Phase 1 open pit mining operations in line with prior expectations.2
•
Increased Mt Ida Lithium Mineral Resource Estimate (MRE) announced:
o
Inferred and Indicated increased to 14.6Mt @ 1.2% Li2O3,
o
136% increase in Indicated Mineral Resources to 7.8Mt @ 1.3 % Li2O2,
o
Increase in the contained lithium positions Delta for a potential 10 year plus mining
operation2.
•
Additionally, a co-located gold MRE of 3.1Mt @ 4.1g/t Au for 412,000 ounces was defined4,
providing an opportunity for early cash flow from a potential sale or toll treatment of gold resources.
•
Delta’s global MRE is now 40.4Mt @ 1.1% Li2O across both projects (at a 0.5% Li2O cut off)
•
A binding agreement was executed with Dalaroo Metals Ltd (ASX: DAL) to purchase the LCT
(lithium, caesium and tantalum) Mineral Rights over its Lyons River Project close to the Yinnetharra
Project area.5
•
An Accelerated Non-Renounceable Entitlement Offer was announced on 13 November 20236 and
completed on 7 December 20237, providing approximately $70.2 million to fund upcoming Company
activities.
•
Cash balance at 31 December 2023 of $116M
Commenting on the quarter, Managing Director of Delta Lithium, Mr James Croser said:
“The final quarter of 2023 saw the achievement of multiple important milestones for the Delta team. An
upgraded MRE at Mt Ida and the declaration of maiden MRE’s for both Yinnetharra and gold at Mt Ida have
all been delivered on schedule. I’m incredibly proud of the speed and skill demonstrated by our team to hit
these targets, especially the MRE at Yinnetharra which has been achieved in just over 12 months from
finalisation of the acquisition.
Refer announcement entitled “Yinnetharra Lithium Project Maiden Mineral Resource Estimate” 27 December 2023
Refer announcement entitled “Mt Ida Lithium Project receives Approval of Mining Proposal and Mine Closure Plan” 3 November 2023
Refer announcement entitled “Mt Ida Lithium Project Mineral Resource Estimate Upgrade” 3 October 2023
4
Refer announcement entitled “Mt Ida Maiden Gold Mineral Resource Estimate” 11 October 2023
5
Refer announcement entitled “Delta acquires LCT Mineral Rights at the Lyons River Project” 1 December 2023
6
Refer announcement entitled “Delta to raise ~A$70 million via fully underwritten ANREO” 13 November 2023
7
Refer announcement entitled “Successful Completion of Retail Component of Entitlement Offer” 7 December 2023
1
2
3
1
ASX ANNOUNCEMENT
23 January 2024
The persistent downtrend and current weak lithium market pricing has given us cause to reassess our
capital allocations. Delta is committed to prudent capital management and we will look to prioritise
Yinnetharra exploration with a view to growing confidence in our larger asset while we consider
development options for Mt Ida.
The Company is planning for success and actively looking for growth opportunities, and we are confident
that 2024 will continue to deliver exciting progress for Delta Lithium.”
YINNETHARRA LITHIUM PROJECT
Exploration and Resource Development
On 27 December 2023, the Company released a maiden Mineral Resource Estimate for the Yinnetharra
Lithium Project located in the Gascoyne Lithium Province of Western Australia. An initial maiden resource
of 25.7Mt @ 1.0% Li2O at a cut-off grade of 0.5% Li2O has been defined solely from the Malinda Prospect.
The potential scale of the total Yinnetharra Project is self-evident when considering multiple untested
outcropping LCT pegmatites in the region that are planned for drill testing in the future.
Table 1: Mineral Resource Estimate for Yinnetharra Lithium Project.
Yinnetharra Lithium December 2023
Resource
category
Cut-off
Grade
grade
(Li2O%)
M1
M36
M42
M47
M69
Measured
Indicated
Inferred
Total Resource
Measured
Indicated
Inferred
Total Resource
Measured
Indicated
Inferred
Total Resource
Measured
Indicated
Inferred
Total Resource
Measured
Indicated
Inferred
Total Resource
Total Measured
Total Indicated
Total Inferred
Total
Ta2O5
Li2O
0.5
0.5
0.5
0.5
0.5
Tonnes
(Mt)
4.5
11.5
16.0
Grade
(% Li2O)
1.1
1.0
1.0
Li2O
(Kt)
48
110
158
1.6
3.4
5.0
0.7
1.0
0.9
11
35
46
46
84
71
0.4
0.4
0.7
0.7
3
3
146
146
0.6
2.7
3.3
1.0
0.9
0.9
6
25
31
99
111
108
0.8
0.8
6.7
19.0
25.7
0.9
0.9
1.0
1.0
1.0
7
7
65
181
246
76
76
(ppm Ta2O5)
45
48
47
51
67
62
Notes:
Tonnages and grades have been rounded to reflect the relative uncertainty of the estimate. Inconsistencies
in the totals are due to rounding.
2
ASX ANNOUNCEMENT
23 January 2024
Figure 1 1 Plan of drillholes and classified block models at Yinnetharra with Indicated (RED) and Inferred (GREEN) Mineral
Resource categories.
The rapid definition and delivery of this MRE in just over 12 months from acquisition paves the way for
subsequent development activities for the project to commence. Exploration remains ongoing with soil
sampling, rock chip sampling and mapping throughout the wider Yinnetharra project area.
Permitting activities and baseline environmental studies and an enhanced drill program will all proceed in
parallel beginning in the new year.
Significant drill results received during the December quarter from drilling at Yinnetharra included;
o
o
o
o
o
o
o
o
68.9m @ 1% Li2O from 128m in YDRD018
47.3m @ 1.3% Li2O from 82.6m in YDRD011
44m @ 0.84% Li2O from 3m in YDRD249
18.5m @ 1.1% Li2O from 64.8m in YDRD014
25.5m @ 0.8% Li2O from 38m in YDRD015
10m @ 1.3% Li2O from 256m in YRRD227
27.9m @ 1.1% Li2O from 158m in YDRD017
21.0m @ 1.2% Li2O from 165m in YRRD260
Jamesons Tenement
The tenement application over E09/2621 being the Jamesons prospect was granted during the quarter.
Cultural heritage surveys are scheduled to be conducted late in 1Q2024 with drilling expected to commence
immediately thereafter.
Soil sampling and mapping at Yinnetharra has been ongoing for some time with the ultimate objective of
evolving our understanding of all Delta tenures and generate a flow of new lithium prospects in our
exploration pipeline. Soil sampling so far has defined good coherent lithium anomalies at Jamesons,
Calypso East and Malinda South. These targets will be drilled once heritage clearances are received for
these specific areas.
3
ASX ANNOUNCEMENT
23 January 2024
Figure 2 Jamesons, Calypso East and Malinda South Li soil anomalies
MT IDA LITHIUM PROJECT
Approval of Mining Proposal and Mine Closure Plan
The Company passed a significant milestone during the December quarter, receiving approval from the WA
Department of Energy, Mines, Industry, Regulations and Safety (DEMIRS) for Phase 1 open pit mining
operations at Mt Ida.
The Mining Approval of open pit mining now positions the Company to take full advantage of the opportunity
to exploit any shallow gold resources that is adjacent to the lithium resource. At this stage of the price cycle
it is not feasible to commence DSO lithium mining as previously announced. The Company maintains the
optionality to do so and will continually assess lithium market conditions in this regard.
Detailed technical work is ongoing based on the recent Lithium MRE update and the maiden Gold MRE
announced by the Company.
Exploration and Resource Development
The Mt Ida Lithium Project updated and upgraded the Mineral Resource Estimate to 14.6Mt @ 1.2% Li2O
in October 2023. The Company is pleased with this result, which importantly include a 136% increase in
Indicated Mineral Resources to 7.8Mt @ 1.3 % Li2O.
4
ASX ANNOUNCEMENT
23 January 2024
Table 22: Mineral Resource Estimate for Mt Ida Lithium Project.
Mt Ida Lithium September 2023
Cut-off
Resource category
Tonnes
Grade
Li2O
Grade
(Li2O%)
(Mt)
(% Li2O)
(Kt)
(Ta2O5 ppm)
-
-
-
-
1.3
1.0
14
189
1.2
0.9
11
144
Total Resource
2.5
1.0
25
167
Measured
-
-
-
-
1.5
1.2
18
206
1.3
1.1
14
156
Total Resource
2.7
1.2
32
183
Measured
-
-
-
-
5.0
1.4
72
238
4.3
1.2
50
156
9.3
1.3
123
200
Total Measured
-
-
-
-
Total Indicated
7.8
1.3
104
224
Total Inferred
6.8
1.1
76
154
Total
14.6
1.2
180
191
Indicated
Inferred
0.55
Indicated
Timoni
Inferred
0.55
Indicated
Sister Sam
Ta2O5
grade
Measured
Sparrow
Li2O
Inferred
Total Resource
0.55
Notes:
Tonnages and grades have been rounded to reflect the relative uncertainty of the estimate. Inconsistencies in the
totals are due to rounding.
In addition to the lithium MRE upgrade, Delta released a maiden Inferred and Indicated Mineral Resource
Estimate for gold at Mt Ida of 3.1Mt @ 4.1g/t Au for 412,000 ounces. It is worth noting that 50% of the gold
MRE is in the higher confidence Indicated Resource category and approximately 85% of the gold MRE is
co-located adjacent to the defined lithium MRE. This proximity potentially de-risks the development of Mt
Ida by generating early cash flow via sale or toll treatment of high grade, shallow gold resources for minimal
incremental cost.
This maiden MRE includes two shallow high-grade discoveries, the Baldock 086 lode and the Meteor North
140 lode.
Baldock 086
High-grade shallow gold resource of 0.24Mt @ 9g/t Au for 70koz potentially amenable to open pit mining
and in close proximity to the top of the Sister Sam lithium resource.
Meteor North 140
High-grade shallow gold resource located just north along strike from the Timoni lithium resource of 0.6Mt
@ 4.7g/t Au for 91koz, also with potential to mine via open pit.
5
ASX ANNOUNCEMENT
23 January 2024
Table 3: Mt Ida Lithium Project; global gold Mineral Resource.
Cut-off
Au g/t
0.5 Open Pit
1.5 Underground
Prospect
Classification
Combined
Indicated
Inferred
Total
Tonnes
Mt
1.12
1.97
3.10
Grade
Au g/t
5.7
3.2
4.1
Metal
Au koz
206
206
412
The Company is considering multiple options to realise value from the gold resources at Mt Ida.
MT IDA
14.6Mt @ 1.2% Li2O
3.1Mt @ 4.1g/t Au
Figure 3: Plan view for gold Mineral Resources location at the Mt Ida Lithium Project
6
ASX ANNOUNCEMENT
23 January 2024
Baldock 086 Lode
Meteor North 140 Lode
Figure 4: Oblique 3D view of drillholes and gold block models and Li bock models at Mt Ida coloured by grade
Drilling results received from the Mt Ida Lithium Project during the quarter included;
o
12m @ 1.6% Li2O from 203m in SPRD051
o
11m @ 1.52% Li2O from 92m in GCS0030
o
11m @ 1.3% Li2O from 75.7m in IDRD197
o
7m @ 1.1% Li2O from 35m in AURD010
And also more high-grade Gold:
o
4m @ 41.2 g/t Au from 79m in GCS0068
o
11m @ 7.3 g/t Au from 68m in GCS0049
o
5m @ 12 g/t Au from 66m in GCS0047
o
3m @ 17.3 g/t from 71m in GCS0051
CORPORATE
Accelerated Non-Renounceable Entitlement Offer
An Accelerated Non-Renounceable Entitlement Offer was announced on 13 November 2023 and
completed on 7 December 2023, raising approximately $70.2 million before costs. The capital raising leaves
the Company well funded to execute its future work programs.
The New Shares subscribed for pursuant to the Retail Entitlement Offer were allotted and issued on Monday
11 December 2023.
7
ASX ANNOUNCEMENT
23 January 2024
Binding agreement with Dalaroo Metals Ltd
In December of 2023, the Company entered a Binding agreement with Dalaroo Metals Ltd (ASX: DAL) to
purchase the LCT (lithium, caesium and tantalum) Mineral Rights over its Lyons River Project in the
Gascoyne region of Western Australia.
The Lyons River Project tenements cover 838 km2 and is located to the southwest of Delta’s existing
Yinnetharra Project. The geology contains similar granite intrusives and sediment-mafic packages that host
the significant Li2O mineralisation at Yinnetharra. As a result of this transaction, Delta’s lithium footprint in
the emerging Gascoyne lithium province has increased by 161% to 1,356 km 2. These tenements have
previously shown early encouraging signs with mapped pegmatite swarms and lithium in soil anomalies up
to 334 ppm Li2O.
Figure2 5 Plan showing location of Yinnetharra Project.
Early exploration activities are planned for the DAL tenure alongside continued exploration at Yinnetharra
in the first quarter of 2024.
Lithium marketing and business development
During the quarter the Company continued to engage with potential offtake partners and the broader global
lithium supply chain.
8
ASX ANNOUNCEMENT
23 January 2024
ASX Compliance
For the purpose of Listing Rule 5.3.2, the Company confirms that there were no mining production and
development activities during the quarter by the Company or its subsidiaries.
In accordance with section 6 of the Appendix 5B, the Company advises that $205k was paid to related
parties of the entity and their associates during the quarter, including Executive and Non-Executive Director
fees.
Release authorised by the Board of Delta Lithium Limited.
For further information, please contact:
Delta Lithium
James Croser, Executive Director
Peter Gilford, CFO & Company Secretary
+61 8 6109 0104
info@deltalithium.com.au
Investor/Media Enquiries
Citadel-MAGNUS
Michael Weir +61 402 347 032
Jono van Hazel +61 411 564 969
About Delta Lithium
Delta Lithium (ASX: DLI) is an exploration and development company focused on bringing high-quality, lithium-bearing pegmatite deposits, located
in Western Australia, into production. With current global JORC compliant resourcesa of 40.4Mt@1.1%Li2O, strong balance sheet and an
experienced team driving the exploration and development workstreams, Delta Lithium is rapidly advancing its Lithium Projects. The Mt Ida Lithium
Project holds a critical advantage over other lithium developers with existing Mining Leases and an approved Mining Proposal. Delta Lithium is
pursuing a development pathway to unlock maximum value for shareholders.
Delta Lithium also holds the highly prospective Yinnetharra Lithium Project that is already showing signs of becoming one of Australia’s most
exciting lithium regions. The Company is currently recommencing exploration activities at Yinnetharra after the Christmas break, and an extensive
multi-rig campaign will be ongoing throughout 2024 to test additional targets and build on the Maiden Resource released in December 2023.
Competent Person's Statement
Information in this Announcement that relates to exploration results is based upon work undertaken by Mr. Charles Hughes, a Competent Person
who is a Member of the Australasian Institute of Mining and Metallurgy (AUSIMM). Mr. Hughes has sufficient experience that is relevant to the style
of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as a ‘Competent Person’ as defined
in the 2012 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’ (JORC Code). Mr. Hughes
is an employee of Delta Lithium Limited and consents to the inclusion in this announcement of the matters based on his information in the form and
context in which it appears.
Refer to www.deltalithium.com.au for past ASX announcements.
Past Exploration results and Mineral Resource Estimates reported in this announcement have been previously prepared and disclosed by Delta
Lithium in accordance with JORC 2012. The Company confirms that it is not aware of any new information or data that materially affects the
information included in these market announcements. The Company confirms that the form and content in which the Competent Person's findings
are presented here have not been materially modified from the original market announcement, and all material assumptions and technical
parameters underpinning Mineral Resource Estimates in the relevant market announcement continue to apply and have not materially changed.
Refer to www.deltalithium.com.au for details on past exploration results and Mineral Resource Estimates.
Disclaimer
This release may include forward-looking and aspirational statements. These statements are based on Delta Lithium management’s expectations
and beliefs concerning future events as of the time of the release of this announcement. Forward-looking and aspirational statements are necessarily
subject to risks, uncertainties and other factors, some of which are outside the control of Delta Lithium, which could cause actual results to differ
materially from such statements. Delta Lithium makes no undertaking to subsequently update or revise the forward looking or aspirational statements
made in this release to reflect events or circumstances after the date of this release, except as required by applicable laws and the ASX Listing
9
ASX ANNOUNCEMENT
23 January 2024
Appendix 1 – Tenement Listing
Project
Location
Tenement
Status
Eureka
Eureka
Eureka
Eureka
Eureka
Eureka
Eureka
Eureka
Lockeridge
Mt Ida
Mt Ida
Mt Ida
Mt Ida
Mt Ida
Mt Ida
Mt Ida
Mt Ida
Mt Ida
Mt Ida
Mt Ida
Mt Ida
Mt Ida
Mt Ida
Mt Ida
Mt Ida
Mt Ida
Mt Ida
Mt Ida
Mt Ida
Mt Ida
Mt Ida
Mt Ida
Mt Ida
Mt Ida
Mt Ida
Mt Ida
Mt Ida
Mt Ida
Mt Ida
Mt Ida
Mt Ida
Mt Ida
Mt Ida
Mt Ida
Mt Ida**
Mt Ida**
Mt Ida**
Mt Ida**
Mt Ida**
Yinnetharra
Yinnetharra
Yinnetharra
Yinnetharra
Yinnetharra
Western Australia
Western Australia
Western Australia
Western Australia
Western Australia
Western Australia
Western Australia
Western Australia
Western Australia
Western Australia
Western Australia
Western Australia
Western Australia
Western Australia
Western Australia
Western Australia
Western Australia
Western Australia
Western Australia
Western Australia
Western Australia
Western Australia
Western Australia
Western Australia
Western Australia
Western Australia
Western Australia
Western Australia
Western Australia
Western Australia
Western Australia
Western Australia
Western Australia
Western Australia
Western Australia
Western Australia
Western Australia
Western Australia
Western Australia
Western Australia
Western Australia
Western Australia
Western Australia
Western Australia
Western Australia
Western Australia
Western Australia
Western Australia
Western Australia
Western Australia
Western Australia
Western Australia
Western Australia
Western Australia
L24/0234
M24/0189
M24/0584
M24/0585
M24/0586
P24/5116
P24/5548
P24/5549
E69/3871
E29/0640
E29/0771
E29/0895
E29/0944
E29/0964
E29/1238
E29/1239
E29/1240
M29/0002
M29/0094
M29/0165
M29/0422
M29/0429
M29/0444
P29/2394
P29/2397
P29/2398
P29/2399
P29/2400
P29/2401
P29/2402
P29/2403
P29/2404
P29/2405
P29/2406
P29/2407
P29/2487
P29/2529
P29/2666
P29/2667
P29/2668
P29/2669
L29/166
L29/171
L29/186
L29/174
L29/175
L29/176
L29/177
L30/094
E09/2169
E09/2170
E09/2283
E09/2545
E09/2621
Granted
Granted
Granted
Granted
Granted
Granted
Granted
Granted
Surrendered
Granted
Granted
Granted
Granted
Granted
Application
Application
Application
Granted
Granted
Granted
Granted
Granted
Application
Granted
Granted
Granted
Granted
Granted
Granted
Granted
Granted
Granted
Granted
Granted
Granted
Granted
Granted
Granted
Granted
Granted
Granted
Granted
Granted
Application
Granted
Granted
Granted
Granted
Granted
Granted
Granted
Granted
Granted
Granted
Interest at start
of Quarter
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
0%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
Interest at end
of Quarter
100%
100%
100%
100%
100%
100%
100%
100%
0%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
10
ASX ANNOUNCEMENT
23 January 2024
Yinnetharra
Yinnetharra
Yinnetharra
Yinnetharra
Yinnetharra
Yinnetharra
Lyons River
Western Australia
Western Australia
Western Australia
Western Australia
Western Australia
Western Australia
Western Australia
E09/2705
E09/2716
E09/2772
E09/2806*
E09/2808*
E09/2814
E09/18241
Application
Application
Application
Application
Application
Application
Granted
100%
100%
100%
100%
100%
100%
0%
100%
100%
100%
100%
100%
100%
100%
Lyons River
Western Australia
E09/18251
Granted
0%
100%
Lyons River
Western Australia
E09/2098
1
Granted
0%
100%
Lyons River
Western Australia
E09/21021
Granted
0%
100%
Lyons River
Western Australia
E09/2304
1
Granted
0%
100%
Lyons River
Western Australia
E09/23051
Granted
0%
100%
Lyons River
Western Australia
E09/23121
Granted
0%
100%
Lyons River
Western Australia
*Application remains in ballot
E09/2713
Granted
0%
100%
1
**Miscellaneous Licences are for the purpose for groundwater search only
1
100% LCT (lithium-caesium-tantalum) Mineral Rights only
Changes:
•
E69/3871 Earaheedy. Surrendered 1 December 2023
•
E29/1238, 1239 & 1240 changed to 100% at beginning of Quarter
•
L29/186 (GV pipeline access). Applied for in Quarter
•
Dalaroo tenements – in list, LCT mineral rights only
•
L29/176 & 177 granted during the Quarter
•
E09/2621 granted during the Quarter
11