Quarterly Activities Report
Released
Released
Announcement PDF
ASX ANNOUNCEMENT
29 July 2024
JUNE QUARTERLY ACTIVITIES REPORT
Delta Lithium Limited (ASX: DLI) (“Delta” or the “Company”) is pleased to provide the following report on
activities undertaken during the June Quarter, 2024.
June Quarter Highlights
•
Major Mineral Resource Estimate (MRE) upgrade of 82% increase in contained gold for Mt Ida.
Inferred and Indicated Mineral Resources of:
6.6Mt @ 3.5 g/t Au for 752,000 ounces (at various cut-off grades see Table 3)
•
Mt Ida gold MRE includes the high-grade Baldock Deposit 4.8Mt @ 4.4g/t Au for 674,000 ounces1
•
Positive metallurgical results from Mt Ida gold testwork
o
•
average 95% recovery and 54% gravity gold from Baldock Deposit
Continued exploration success with drilling results from the Yinnetharra Project demonstrating
quality lithium intercepts including 2,3:
o
94m @ 0.94% Li2O from 152m in YRRD471 at M1
o
43m @ 1.1% Li2O from 128m in YRRD478 at M1
o
21m @ 2.1% Li2O from 206m in YRRD458 at M36
28m @ 1.8% Li2O from 194m in YRRD534 at M36
First drilling at Jameson delivered encouraging results. Best drilling intercepts to date include2,3:
o
71m @ 1.2% Li2O from 27m in JREX002 (not true width)
o
18m @ 1.5% Li2O from 13m in JREX012
o
•
22m @ 1.4% Li2O from 135m in YRRD470 at M1
o
o
•
Including 34m @ 2% Li2O from 197m
including 45m @ 1.8% Li2O from 41m
16m @ 1.7% Li2O from 26m in JREX001
Positive metallurgical testwork results (Low-grade variability) from M1 at Malinda
o
Metallurgical testwork to Definitive Feasibility Study (DFS) level of detail on the M1 underway
Commenting on the quarter, Managing Director of Delta Lithium, Mr James Croser said:
“A number of key workstreams at Delta’s Yinnetharra and Mt Ida projects have advanced during the quarter
and exploration has yielded brilliant results at both sites.
Drilling at Yinnetharra’s Malinda prospect has continued to build confidence, and results from RC drilling at
Jamesons prospect delivered some very promising lithium assays. Further metallurgy on the M1 at Malinda
showed encouraging lithium recoveries to a spodumene concentrate despite lower grade cutoffs. We also
completed the compilation of a 5t pilot plant sample to support ongoing feasibility studies.
1 Refer ASX Announcement 28 June 2024 titled “Mt Ida Gold MRE Update”
2 Refer ASX Announcement 22 April 2024 titled “Company Update and First Jameson Result”
3 Refer ASX Announcement 20 June 2024 titled “Yinnetharra Exploration Update”
1
ASX ANNOUNCEMENT
29 July 2024
Mt Ida continues to deliver fantastic surprises with a major upgrade to the high-grade gold resource to
752koz, underpinning real optimism for the potential of the gold to deliver strong shareholder value.
Dedicated gold drilling will be undertaken in the coming quarter to target further ounces.”
YINNETHARRA LITHIUM PROJECT
Exploration and Resource Development
The Yinnetharra project is in the Gascoyne region of Western Australia targeting Lithium mineralisation.
Delta Lithium has 1,769km2 of tenure owned outright and as Farm-in Joint Ventures. A maiden MRE was
released in December 2023 of 25.7Mt @ 1% Li2O 4. Farm-In Joint Venture Agreements have expanded the
prospective stratigraphy to over 80km in length. The Company has continued to actively explore at
Yinnetharra with two (2) drill rigs currently operating at the Malinda prospect, supported by multiple field
teams undertaking detailed geological mapping and surface sampling. Ongoing exploration will support the
expansion and further definition of target prospects across the wider Yinnetharra package of tenure.
Figure 1: Location of Yinnetharra Project
4 Refer ASX Announcement 27 December 2024 titled “Yinnetharra Lithium Project Maiden Mineral Resource Estimate”
2
ASX ANNOUNCEMENT
29 July 2024
Drilling completed to date at Malinda has demonstrated quality lithium intercepts over a strike length in
excess of 2km, from surface and in some cases extending to below 300m depth. Recent highlights can be
seen below in Table 1 and Figures 2 & 3. Further along strike extensions to M36 have been found, as well
as near surface eastern extensions to M42 and a new near surface mineralised pegmatite in M20.The
Company is very pleased with the results received to date.
HoleID
JREX002
YRRD471
YRRD534
YRRD478
YRRD458
YRRD470
YRRD612
JREX012
JREX001
YRRD516
YRRD425
YRRD617
YRRD479B
YRRD596
YRRD538
YRRD618
YRRD611
YRRD608
YDRD054
YRRD615
YDRD053
YRRD633A
JREX016
From
including
including
27
41
152
197
194
128
206
135
140
13
26
6
169
141
193
106
199
152.5
93
152
174.5
13
89
150
112
To
98
86
246
231
222
171
227
157
162
31
42
30
195
165
212
126
211
170.6
108
167
185.8
24
100
159
119
Length
71
45
94
34
28
43
21
22
22
18
16
24
26
24
19
20
12
18.1
15
15
11.3
11
11
9
7
Li2O pct
1.2
1.8
0.94
2.0
1.8
1.1
2.1
1.4
1.3
1.5
1.7
1.1
1.0
1.1
1.3
1.1
1.6
1.0
1.2
1.1
1.4
1.4
1.3
1.3
1.4
Ta2O5
ppm
62
56
37
37
63
48
126
52
67
27
31
98
47
52
15
25
98
59
34
45
29
97
26
46
60
Fe2O3 pct
0.95
0.8
1.4
1.0
1.0
0.8
1.4
1.2
0.9
2.1
0.7
1.1
0.7
2.7
1.1
1.9
0.9
1.2
1.0
1.0
0.7
1.1
0.7
4.2
0.8
Table 1: Significant Li Intercepts from Yinnetharra >1.0% Li20
3
ASX ANNOUNCEMENT
29 July 2024
Figure 2: Malinda Plan view showing block models with selected recent intercepts
Jameson Prospect
The Company commenced drilling at the Jameson project and received results early in the June quarter.
The results demonstrate spodumene bearing pegmatites present from surface. Stratigraphy at the Jameson
prospect is folded. Lithium anomalism at Jameson is present as a coherent soil geochemistry anomaly
>150ppm Li2O approximately 600m long parallel with stratigraphy. Pegmatites cross-cut the stratigraphy
trending NE-SW. Drilling orientations at Jameson were initially chosen to intercept the regional trend of
stratigraphy in a perpendicular manner, access considerations and a desire to test pegmatite orientations
account for the variety of drill hole orientations.
Early drilling has returned encouraging results showing some of the most coarse spodumene to date at
Yinnetharra. Best assays so far include:
•
71m @ 1.2% Li2O from 27m in JREX002 including 45m @ 1.8% Li2O from 41m (not true width)
•
18m @ 1.5% Li2O from 13m in JREX012
•
16m @ 1.7% Li2O from 26m in JREX001
The J1 pegmatite at Jamesons does present with some complexity around the folded stratigraphy. Further
drilling is required to determine the true setting.
4
ASX ANNOUNCEMENT
29 July 2024
Figure 3: Plan showing location of Jamesons
Joint Ventures
Delta signed binding agreements earlier this year with both Voltaic Strategic Resources Ltd (ASX: VSR)
and Reach Resources Limited (ASX: RR1) to Earn-In ownership of tenement packages. The new land
packages cover an additional 413km2 and are positioned adjacent to and along strike of the already defined
resource at Malinda, within the 100% owned Yinnetharra Lithium Project.
Delta has commenced groundwork on the joint venture tenements during the quarter. The groundwork
consists of a methodical approach of mapping and soil sampling to identify potential drill targets.
Yinnetharra Project Development
Environmental baseline studies are ongoing at Yinnetharra including flora and fauna, materials
characterisation, surface and groundwater studies. These studies will be ongoing for the balance of
CY2024 with a view to determining the permitting route by the end of CY2024 in collaboration with the
relevant Government Agencies.
Targeted geotechnical drilling in conjunction with the identification and acquisition of core for metallurgical
variability testwork across the Malinda orebody will be incorporated into the drilling schedule for the next
several quarters. Water exploration drilling will also be undertaken in the second half of CY2024.
5
ASX ANNOUNCEMENT
29 July 2024
A metallurgical test work programme to a DFS level of detail was approved by the Delta Board late in the
Quarter to target the M1, M36 and M47 pegmatite orebodies in respective order. Current work underway
on the M1 sample composites will also incorporate a 5 tonne pilot plant test. This test work will be ongoing
for the remainder of CY2024 and is expected to be completed early in the March Quarter of 2025. Material
results will be reported as they become available.
Delta has engaged engineering company Primero to complete a Pre-Feasibility Study (PFS) level of Detail
on the Processing Plant design. The intent of this PFS is that the deliverables (Process Design Criteria,
Process Flow Diagram, Mass Balance etc) can be used for tendering an EPC Style of Contract the detailed
design and construction of the Process Plant. This PFS study will occur concurrently with the metallurgical
test work programme.
A scoping level study is underway at Yinnetharra based only on the maiden Mineral Resource Estimate at
Malinda. The results of the Scoping Study are expected to be released in the December Quarter of 2024.
Malinda Metallurgy
Delta is completing further metallurgical work to improve the understanding of the ore body variability and
to better estimate laboratory scale up factors. Subsequent to the initial test work on M1 and M47 composite
samples (see ASX announcement 21/08/2023), the Company has recently completed a limited number of
scoping batch flotation tests on low grade M1 ore composites from 0.6% to 1% Li2O. The Low Grade
Variability composites were developed from M1 drill core and were specifically chosen to evaluate the
preliminary processing flowsheet to treat mineralised material with grade between the resource cutoff grade
and the potential mining cutoff grade, as can reasonably be expected to be included in the ore stream via
mining dilution.
The results of the Low Grade Variability testwork (Table 2) showed encouraging global recoveries between
70-84% for the bench-scale batch tests. It should be noted that for comparative purposes, in contrast to the
‘Sighter Testwork’ the ‘Low Grade Variability’ tests did not include a magnetic separation stage in the
testwork flowsheet. Delta plans to include a magnetic separation stage to manage concentrate iron grades
in future workstreams.
Current testwork being undertaken employs a whole of ore flotation flowsheet, where crushed ore is milled
to p80 106 µm before desliming and magnetic separation. The non-magnetic material then feeds a mica
preflotation stage which precedes spodumene flotation.
This current testwork is focussing on spatial and geometallurgical domain variability testing of the M1
pegmatite. The scope of work includes specific testing addressing early mine phases as well as exploring
opportunities to simplify the existing process flowsheet. The planned work includes locked cycle flotation
testwork and a pilot plant treating 5 tonnes of ore. The pilot testing aims to validate the final flowsheet and
provide better estimates for batch test scale up factors. Drilling of PQ core and collection of the pilot sample
is approaching completion as at the end of the quarter.
Similar geometallurgical domain variability testwork is planned for the M36 and M47 pegmatites and
compilation of sample will be achieved in the next Quarter.
6
ASX ANNOUNCEMENT
29 July 2024
Pegmatite
Test
Comp
Head Feed
Mags & Slimes
Grade
Flot. Feed
Grade
Mica. Con
Spod. Con
Grade
Rec
Grade
Rec
Grade
(%
(%
(%
(%
(%
(%
(%
(%
(%
(%
Rec
(%
Li O)
2
Fe O )
2 3
Li O)
2
Li O)
2
Li O)
2
Fe O )
2 3
Li O)
2
Li O)
2
Li O)
2
Fe O )
2 3
Li O)
2
M47
A1
2.30
0.13
1.77
10.17
2.24
0.31
2.92
19.6
6.55
0.09
61.8
M1
A2
0.97
0.27
0.77
13.46
0.94
0.50
0.33
5.5
6.57
0.41
77.3
M47
A3
2.30
0.13
1.77
10.17
2.29
0.50
2.64
20.3
6.55
0.08
61.0
M1
A4
0.97
0.27
0.77
13.46
1.02
0.31
0.24
5.6
6.81
0.40
75.0
M1 LG Var 1
SF1
0.51
0.30
0.35
12.9
0.59
0.37
0.38
13.4
5.44
1.53
71.5
M1 LG Var 2
SF2
0.59
0.22
0.33
8.9
0.68
0.32
0.26
5.7
5.73
1.24
84.7
M1 LG Var 3
SF3
0.69
0.19
0.38
8.5
0.82
0.29
0.34
5.5
6.14
1.05
84.5
M1 LG Var 4
SF4
0.85
0.32
0.47
8.4
0.93
0.38
0.47
7.1
5.12
1.11
83.4
Note: magnetic separation stage not used in M1 LG Var testwork
Table 2: Flotation metallurgical test work results
MT IDA PROJECT
The Company announced a major Mineral Resource Estimate (MRE) upgrade for gold at Mt Ida. The update
to the MRE was the result of additional drilling completed by Delta subsequent to the release of the Maiden
Mt Ida Gold MRE on 11 October 2023 and 199 historical drillholes for 11,830m at Golden Vale.
The upgraded JORC compliant, Inferred and Indicated Mineral Resources of:
6.6Mt @ 3.5 g/t Au for 752,000 ounces (at various cut-off grades see Table 3)
This MRE upgrade represents an 82% increase in contained gold for the Mt Ida Project with the new Mineral
Resource Estimate (MRE) prepared by independent external Consultant Snowden Optiro. The upgrade
included 82% Increase in the Baldock Deposit to 4.8Mt @ 4.4g/t gold for 674,000 ounces and also a
Maiden Mineral Resource Estimate for the Golden Vale Prospect of 27,000 ounces @ 1.7g/t Au.
See JORC table by Deposit below in Table 3.
Mt Ida Gold Mineral Resource Estimate
Indicated
Cut off
Open cut Au
0.5 g/t
0.0 g/t Au Cut
off
Underground
1.5 g/t Au
Deposit
Inferred
Grade
Ounces
Tonnes
Grade
Ounces
Tonnes
Grade
Ounces
(000s)
g/t Au
(000s)
(000s)
g/t Au
(000s)
(000s)
g/t Au
(000s)
Baldock
1,345
4.9
209.0
1,512
3.2
158
2,857
4.0
367
Kestrel
-
-
-
570
1.6
29
570
1.6
29
Golden Vale
-
-
-
496
1.7
27
496
1.7
27
Mt Ida Tailings
-
-
-
500
0.5
8
500
0.5
8
Baldock
180
5.8
33.0
1,780
4.8
274
1,960
4.9
307
Kestrel
-
-
-
220
1.9
14
220
1.9
14
Golden Vale
-
-
-
Mt Ida Tailings
All
Total
Tonnes
-
-
-
-
-
-
500
0.5
8
500
0.5
8
Baldock
1,525
4.9
242.0
3,292
4.1
432
4,817
4.4
674
Kestrel
-
-
-
790
1.7
43
790
1.7
43
Golden Vale
Total
-
-
-
496
1.7
27
496
1.7
27
1,525
4.9
242.0
5,078
3.1
510
6,603
3.5
752
Table 3: June 2024 Mt Ida Gold mineral resource estimate JORC table
7
ASX ANNOUNCEMENT
29 July 2024
Key changes to the Mineral Resource Estimate released on 11 October 2023 are:
•
A more conservative approach to reporting of MRE has been taken, in accordance with Reasonable
Prospects of Eventual Economic Extraction (RPEEE) guidelines to the JORC2012 Code
•
Mineralisation previously referred to as “Western Lodes” now referred to as the Baldock Deposit
•
82% Increase in the overall MRE for the Mt Ida Project from 412koz @ 4.1 g/t Au to 752koz @ 3.5
g/t Au
•
82% Increase in the overall MRE for the Baldock Deposit from 370koz to 674koz
o
17% Increase in total Indicated Resources from 206koz @ 5.7 g/t Au to 242koz @ 4.9 g/t Au
o
153% Increase in open cut Resources reported into an optimised ultimate pit shell (reported
at 0.5 g/t Au cut off) from 145koz @ 5.5 g/t Au to 367koz @ 4 g/t Au
o
90% Increase in open cut Indicated Resources reported into an optimised ultimate pit shell
(reported at 0.5 g/t Au cut off) from 110koz @ 6.6g/t Au to 209koz @ 4.8g/t Au
o
36% increase in underground resources reported into optimised stopes (reported at 1.5g/t
Au cut off) from 225koz @ 4.7g/t Au to 307koz @ 4.9 g/t Au
•
Addition of maiden Golden Vale MRE of 27koz @ 1.7 g/t Au reported into an optimised ultimate pit
shell at 0.5 g/t Au cut off
•
No change to Kestrel MRE of 43koz
Baldock Deposit
The Baldock deposit is a series of steeply west-south-west dipping gold lodes in the vicinity of the historic
Baldock and Timoni gold mines, located within Delta’s 100% owned Mt Ida Project (see Figure 4). There is
a close relationship between the Baldock Lodes and the Timoni and Sister Sam lithium deposits (see ASX
announcement dated 3rd October 2023 entitled ‘Mt Ida Lithium Mineral Resource Estimate Update’). Gold
mineralisation is associated with quartz and sulphide development within shear zones. The MRE extends
over 2km of strike, with the mineralised system identified over 4km of strike with only a handful of holes
testing the strike outside the MRE (See Figure 4).
8
ASX ANNOUNCEMENT
29 July 2024
Figure 4: Long section showing Baldock Deposit MRE with mineralised drillholes present outside of the resource.
Potential Resource Growth
The Company has undertaken very little gold specific exploration at Mt Ida since the acquisition of the
project in 2021 (see ASX Announcement dated 24th September 2021 entitled: ‘Completion of Mt Ida
Acquisition’). The majority of drilling that has been undertaken and used for this gold MRE update was
drilled targeting lithium. In addition to the excellent resource growth potential immediately along strike and
down dip of existing resources at Baldock (See Figure 4), Golden Vale and Kestrel (Maiden Mt Ida Gold
MRE on 11 October 2023), there are numerous drilling results exceeding 1g/t Au within the project that sit
outside current resource estimates (See Figure 5 and Table 3).
Drilling is currently underway at the Mt Ida Project and will target high-grade resource extension
opportunities to grow the resource significantly.
9
ASX ANNOUNCEMENT
29 July 2024
Figure 5: Plan showing simplified geology, position of Gold MRE’s, drilling intercept disks greater than 1g/t Au, intercepts are
reported as downhole length not true width, where possible drilling is normal to orientation of lodes but may not be a reflection of
the true width of mineralisation
Comprehensive metallurgical testwork has been undertaken and received for the Baldock 086 Lode. A total
of 74 spatial variability samples were selected throughout the Baldock 086 lode and sent for comprehensive
testwork to understand gold recovery and cyanide consumption. From these samples three (3) master
composites based on ore types were created; an oxide master comp IM2078, a transitional master comp,
IM2079 and a fresh master comp IM2080.
Gold extraction rates for each ore type are tabulated below in Table 2. A range of 91.4-99.7% recovery was
achieved in an eight hour residence time, with 44-63% of the gold able to be recovered with a gravity circuit.
Cyanide consumption was very low for the master composites ranging from 0.5-1.25 kg/t.
10
ASX ANNOUNCEMENT
29 July 2024
Table 4: Summary metallurgical testwork table for Baldock Lode 086 master composites
Mt Ida Project Development - Gold
Delta is exploring opportunities to monetise the gold resource at Mt Ida. A Scoping Study is underway for
release in the coming quarter, which contemplates mining the gold resource only and preserving the lithium
resource for a future investment decision. The basis of the Scoping Study will be a toll treating or ore
purchase agreement for processing. Preliminary discussions have commenced with third parties regarding
processing options for treatment of the gold with non-binding terms received from several parties
The initial Baldock Open Pits are fully permitted and shovel ready. The Mining Proposal and Mine Closure
Plan has been updated to incorporate an additional open pit at Baldock and the Baldock Underground and
is currently under assessment with DEMIRS.
CORPORATE
Cash and Cash Equivalents
Cash at the end of the quarter was $86.7M.
ASX Compliance
For the purpose of Listing Rule 5.3.2, the Company confirms that there were no mining production and
development activities during the quarter by the Company or its subsidiaries.
In accordance with section 6 of the Appendix 5B, the Company advises that $185k was paid to related
parties of the entity and their associates during the quarter, including Executive and Non-Executive Director
fees.
Release authorised by the Board of Delta Lithium Limited.
For further information, please contact:
Delta Lithium
James Croser, Managing Director
Peter Gilford, CFO & Company Secretary
+61 8 6109 0104
info@deltalithium.com.au
Investor/Media Enquiries
Sodali & Co
Michael Weir +61 402 347 032
11
ASX ANNOUNCEMENT
29 July 2024
About Delta Lithium
Delta Lithium (ASX: DLI) is an exploration and development company focused on bringing high-quality, lithium-bearing pegmatite deposits, located
in Western Australia, into production. With current global JORC compliant resources of 40.4Mt@1.1%Li2O, strong balance sheet and an
experienced team driving the exploration and development workstreams, Delta Lithium is rapidly advancing its Projects. The Mt Ida deposit has
coincident gold and lithium orebodies and holds a critical advantage over other developers with existing Mining Leases and an approved Mining
Proposal. Delta Lithium is pursuing a development pathway to unlock maximum value for shareholders.
Delta Lithium also holds the highly prospective Yinnetharra Lithium Project that is already showing signs of becoming one of Australia’s most
exciting lithium regions. The Company is currently conducting exploration activities at Yinnetharra and an extensive multi-rig campaign will be
ongoing throughout 2024 to test additional targets and build on the Maiden Resource released in December 2023.
Competent Person's Statement
Information in this Announcement that relates to exploration results is based upon work undertaken by Mr. Charles Hughes, a Competent Person
who is a Member of the Australasian Institute of Mining and Metallurgy (AUSIMM). Mr. Hughes has sufficient experience that is relevant to the style
of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as a ‘Competent Person’ as defined
in the 2012 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’ (JORC Code). Mr. Hughes
is an employee of Delta Lithium Limited and consents to the inclusion in this announcement of the matters based on his information in the form and
context in which it appears.
Refer to www.deltalithium.com.au for past ASX announcements.
Past Exploration results and Mineral Resource Estimates reported in this announcement have been previously prepared and disclosed by Delta
Lithium in accordance with JORC 2012. The Company confirms that it is not aware of any new information or data that materially affects the
information included in these market announcements. The Company confirms that the form and content in which the Competent Person's findings
are presented here have not been materially modified from the original market announcement, and all material assumptions and technical
parameters underpinning Mineral Resource Estimates in the relevant market announcement continue to apply and have not materially changed.
Refer to www.deltalithium.com.au for details on past exploration results and Mineral Resource Estimates.
Disclaimer
This release may include forward-looking and aspirational statements. These statements are based on Delta Lithium management’s expectations
and beliefs concerning future events as of the time of the release of this announcement. Forward-looking and aspirational statements are necessarily
subject to risks, uncertainties and other factors, some of which are outside the control of Delta Lithium, which could cause actual results to differ
materially from such statements. Delta Lithium makes no undertaking to subsequently update or revise the forward looking or aspirational statements
made in this release to reflect events or circumstances after the date of this release, except as required by applicable laws and the ASX Listing
No New Information
This document should be read in conjunction with Delta’s other periodic and continuous disclosure announcements lodged with the ASX, which are
available on Delta’s website.
12
ASX ANNOUNCEMENT
29 July 2024
JORC Tables
Table 5: Global Lithium Mineral Resource Estimate Summary Table
Delta Lithium Group Mineral Resource estimate
Cut-off
Resource category
Li2O
Ta2O5
grade
Tonnes
Grade
Li2O
Grade
(Li2O%)
(Mt)
(% Li2O)
(Kt)
(Ta2O5 ppm)
-
-
-
-
6.7
1.0
65
51
19.0
1.0
181
67
Total Resource
25.7
1.0
246
62
Measured
-
-
-
-
7.8
1.3
104
224
6.8
1.1
76
154
14.6
1.2
180
191
Total Measured
-
-
-
-
Total Indicated
14.5
1.2
169
144
Total Inferred
25.8
1.0
257
90
Total
40.4
1.1
426
109
Measured
Indicated
Yinnetharra
0.5
Inferred
Indicated
Mt Ida
0.5
Inferred
Total Resource
Notes:
Tonnages and grades have been rounded to reflect the relative uncertainty of the estimate. Inconsistencies in
the totals are due to rounding.
Table 6: Mt Ida Project; global gold Mineral Resource
Mt Ida Gold Mineral Resource Estimate
Indicated
Cut off
Open cut Au
0.5 g/t
0.0 g/t Au Cut
off
Underground
1.5 g/t Au
Deposit
Inferred
Tonnes
Grade
Ounces
Tonnes
Grade
Ounces
Tonnes
Grade
Ounces
(000s)
g/t Au
(000s)
(000s)
g/t Au
(000s)
(000s)
g/t Au
(000s)
Baldock
1,345
4.9
209.0
1,512
3.2
158
2,857
4.0
367
Kestrel
-
-
-
570
1.6
29
570
1.6
29
Golden Vale
-
-
-
496
1.7
27
496
1.7
27
Mt Ida Tailings
-
-
-
500
0.5
8
500
0.5
8
Baldock
180
5.8
33.0
1,780
4.8
274
1,960
4.9
307
Kestrel
-
-
-
220
1.9
14
220
1.9
14
Golden Vale
-
-
-
-
-
-
-
-
-
500
0.5
8
500
0.5
8
Mt Ida Tailings
All
Total
Baldock
1,525
4.9
242.0
3,292
4.1
432
4,817
4.4
674
Kestrel
-
-
-
790
1.7
43
790
1.7
43
Golden Vale
-
-
-
496
1.7
27
496
1.7
27
1,525
4.9
242.0
5,078
3.1
510
6,603
3.5
752
Total
13
ASX ANNOUNCEMENT
29 July 2024
Appendix 1 – Tenement Listing
Project
Location
Tenement
Status
Interest
at start
of
Quarter
Eureka
Western Australia
L24/0234
Granted
100%
100%
Eureka
Western Australia
M24/0189
Granted
100%
100%
Eureka
Western Australia
M24/0584
Granted
100%
100%
Eureka
Western Australia
M24/0585
Granted
100%
100%
Eureka
Western Australia
M24/0586
Granted
100%
100%
Eureka
Western Australia
P24/5116
Granted
100%
100%
Eureka
Western Australia
P24/5548
Granted
100%
100%
Eureka
Western Australia
P24/5549
Granted
100%
100%
Mt Ida
Western Australia
E29/0640
Granted
100%
100%
Mt Ida
Western Australia
E29/0771
Granted
100%
100%
Mt Ida
Western Australia
E29/0895
Surrendered
100%
0%
Mt Ida
Western Australia
E29/0944
Granted
100%
100%
Mt Ida
Western Australia
E29/0964
Granted
100%
100%
Mt Ida
Western Australia
E29/1238
Granted
100%
100%
Mt Ida
Western Australia
E29/1239
Granted
100%
100%
Mt Ida
Western Australia
E29/1240
Granted
100%
100%
Mt Ida
Western Australia
E29/1262
Application
100%
100%
Mt Ida
Western Australia
M29/0002
Granted
100%
100%
Mt Ida
Western Australia
M29/0094
Granted
100%
100%
Mt Ida
Western Australia
M29/0165
Granted
100%
100%
Mt Ida
Western Australia
M29/0422
Granted
100%
100%
Mt Ida
Western Australia
M29/0429
Granted
100%
100%
Mt Ida
Western Australia
M29/0444
Granted
100%
100%
Mt Ida
Western Australia
P29/2397
Granted
100%
100%
Mt Ida
Western Australia
P29/2398
Granted
100%
100%
Mt Ida
Western Australia
P29/2399
Granted
100%
100%
Mt Ida
Western Australia
P29/2400
Granted
100%
100%
Mt Ida
Western Australia
P29/2401
Granted
100%
100%
Mt Ida
Western Australia
P29/2402
Granted
100%
100%
Mt Ida
Western Australia
P29/2403
Granted
100%
100%
Mt Ida
Western Australia
P29/2404
Granted
100%
100%
Mt Ida
Western Australia
P29/2405
Granted
100%
100%
Mt Ida
Western Australia
P29/2406
Granted
100%
100%
Mt Ida
Western Australia
P29/2407
Granted
100%
100%
Mt Ida
Western Australia
P29/2666
Granted
100%
100%
Interest
at end of
Quarter
14
ASX ANNOUNCEMENT
29 July 2024
Project
Location
Tenement
Status
Interest
at start
of
Quarter
Mt Ida
Western Australia
P29/2667
Granted
100%
100%
Mt Ida
Western Australia
P29/2668
Granted
100%
100%
Mt Ida
Western Australia
P29/2669
Granted
100%
100%
Mt Ida
Western Australia
L29/166
Granted
100%
100%
Mt Ida
Western Australia
L29/171
Granted
100%
100%
Mt Ida
Western Australia
L29/186
Application
10%
100%
Mt Ida**
Western Australia
L29/174
Granted
100%
100%
Mt Ida**
Western Australia
L29/175
Granted
100%
100%
Mt Ida**
Western Australia
L29/176
Granted
100%
100%
Mt Ida**
Western Australia
L29/177
Granted
100%
100%
Mt Ida**
Western Australia
L30/094
Granted
100%
100%
Yinnetharra
Western Australia
E09/2169
Granted
100%
100%
Yinnetharra
Western Australia
E09/2170
Granted
100%
100%
Yinnetharra
Western Australia
E09/2283
Granted
100%
100%
Yinnetharra
Western Australia
E09/2545
Granted
100%
100%
Yinnetharra
Western Australia
E09/2621
Granted
100%
100%
Yinnetharra
Western Australia
E09/2705
Application
100%
100%
Yinnetharra
Western Australia
E09/2716
Application
100%
100%
Yinnetharra
Western Australia
E09/2772
Application
100%
100%
Yinnetharra
Western Australia
E09/2806*
Application
100%
100%
Yinnetharra
Western Australia
E09/2808*
Application
100%
100%
Yinnetharra
Western Australia
E09/2814
Application
100%
100%
Lyons River
Western Australia
E09/18241
Granted
100%
100%
Lyons River
Western Australia
E09/18251
Granted
100%
100%
Western Australia
E09/20981
Granted
100%
100%
Lyons River
Western Australia
E09/21021
Granted
100%
100%
Lyons River
Western Australia
E09/23041
Granted
100%
100%
Lyons River
Western Australia
E09/23051
Granted
100%
100%
Western Australia
E09/23121
Granted
100%
100%
Lyons River
Western Australia
E09/27131
Granted
100%
100%
Camel Hill2
Western Australia
E09/23542
Granted
0%
0%
Camel Hill2
Western Australia
E09/23882
Granted
0%
0%
Lyons River
Lyons River
Morrissey Hill2
Interest
at end of
Quarter
Western Australia
E09/23752
Granted
0%
0%
Morrissey Hill2
Western Australia
M09/1012
Granted
0%
0%
Morrissey Hill2
Western Australia
E09/28052*
Application
0%
0%
Morrissey Hill2
Western Australia
E09/28062*
Application
0%
0%
Western Australia
E09/28972*
Application
Share your feedback
Discover