Half Yearly Report and Accounts
Released
Released
Announcement PDF
DELTA LITHIUM LIMITED
ACN 107 244 039
Interim Financial Report
for the Half-Year Ended
31 December 2023
DELTA LITHIUM LIMITED
Interim Financial Report 31 December 2023
Table of Contents
Corporate Directory ............................................................................................. 2
Director’s Report ................................................................................................ 3
Auditors’ Independence Declaration ............................................................................. 12
Condensed Consolidated Statement of Profit or Loss and Other Comprehensive Income ............................... 13
Condensed Consolidated Statement of Financial Position .......................................................... 14
Condensed Consolidated Statement of Changes in Equity .......................................................... 15
Condensed Consolidated Statement of Cash Flows ................................................................ 16
Directors’ Declaration ......................................................................................... 27
Independent Auditor’s Review Report ........................................................................... 28
1
DELTA LITHIUM LIMITED
Interim Financial Report 31 December 2023
Corporate Directory
Directors
Chris Ellison (Non-Executive Chairman)
James Croser (Managing Director)
Nader El Sayed (Non-Executive Director)
Tim Manners (Non-Executive Director)
Steve Kovac (Non-Executive Director)
Joshua Thurlow (Non-Executive Director)
Company Secretary
Peter Gilford
Registered Office and Principal Place of
Business
Level 2, 18 Richardson Street
West Perth WA 6005
Tel: +61 8 6109 0104
Auditors
KPMG
235 St George's Terrace
Perth WA 6000 Australia
Solicitors
Thomson Geer
Level 29, Central Park
152-158 St Georges Tce
Perth WA 6000
Share Registry
Computershare Investor Services Pty Ltd
Level 17, 221 St Georges Terrace
Perth WA 6000
Australian Telephone: 1300 850 505
International Telephone: +61 3 9415 4000
www.computershare.com.au
Securities Exchange Listing
Delta Lithium Limited shares are listed on the
Australian Securities Exchange (ASX)
ASX Code: DLI
Website
www.deltalithium.com.au
Email
Info@deltalithium.com.au
2
DELTA LITHIUM LIMITED
Interim Financial Report 31 December 2023
Director’s Report
The Directors hereby present their Interim Financial Report on Delta Lithium Limited (ASX: DLI) (the ‘Company’ or ‘Delta’)
and its subsidiaries for the half-year ended 31 December 2023.
DIRECTORS
Except as otherwise stated below, the following persons were Directors of Delta Lithium Limited during the whole of the halfyear and up to the date of this Report as follows:
Director
Chris Ellison
James Croser1
Nader El Sayed
Tim Manners
Steve Kovac
Joshua Thurlow
David Flanagan
1
Title
Non-Executive Chairman
Managing Director
Non-Executive Director
Non-Executive Director
Non-Executive Director
Non-Executive Director
Executive Chairman
Appointment Date
12 September 2023
4 December 2020
1 March 2021
1 March 2022
2 August 2023
12 September 2023
29 August 2022
Resignation Date
12 September 2023
Mr James Croser transitioned from Non-Executive Director to Managing Director on 12 September 2023.
COMPANY SECRETARY
Mr Peter Gilford has acted as the Company Secretary during the entire period.
Review of Operations
Despite the volatile lithium price environment experienced in
the second half of 2023, Delta has continued to surpass
operational goals and advance both the Mt Ida and Yinnetharra
projects.
Conscious of the prevailing lithium market conditions and our
commitment to prudent capital management, Delta made the
strategic decision during the reporting period to place the
plans for early DSO operations at Mt Ida on hold. Investigations
into the production of a lithium concentrate product continue
as previously planned, as does exploration and resource
definition activity on both projects.
The team believes that by prudently refining the knowledge of
the Mt Ida orebody and continuing to define the scale of the
Yinnetharra Project, the Company will be best positioned to
take advantage of the year ahead.
The Delta team has achieved significant operational milestones
during the half-year, including the completion of a maiden
Mineral Resource Estimate (MRE) at Yinnetharra, receiving
approval from the WA Department of Energy, Mines, Industry
Regulation and Safety (DEMIRS) for the Mining Proposal and
Mine Closure Plan and an increased MRE at Mt Ida.
Corporate Strategy
Delta has retained a strategic advantage over many peers by
progressing the status of the Mt Ida Project site from a granted
mining lease to an approved Mining Proposal and Mine Closure Plan. The approval was granted by DEMIRS in the December
quarter of 2023. This positions the Mt Ida Project as shovel ready for commencement of production when the market price
recovers. Co-located to the lithium resource, the definition of the Gold MRE during the half-year provides an additional source
of value for the Company.
Looking forward, the Company is focused on three main objectives:
•
•
•
Developing a production pathway for a Mt Ida Lithium Concentrate product;
Expanding the scale and confidence in the extensive Yinnetharra Project;
Growth via exploration and a disciplined approach to acquisition opportunities and realising Gold value.
3
DELTA LITHIUM LIMITED
Interim Financial Report 31 December 2023
Yinnetharra Lithium Project
The Yinnetharra Lithium Project located in the Gascoyne Lithium Province of Western Australia was acquired by Delta in
September of 2022. The Project sits within a tenement package covering an area of 517.5km2. Throughout the course of 2023
the Company drilled 498 holes for 115,317m at the Malinda Prospect. The Lithium mineralisation at the Malinda Prospect is
predominantly spodumene hosted, contained within multiple north and south shallowly dipping pegmatites.
Figure 1: Yinnetharra plan showing general location of drilling at the Malinda Prospect and the Jameson Prospect.
In December of 2023, the Company reported its maiden Mineral Resource Estimate of Yinnetharra. The rapid definition and
delivery of the MRE in just over 12 months from the acquisition is a significant achievement for the Company reflecting the
experience and strength of the exploration team.
The combined Inferred and Indicated Mineral Resource Estimate were measured as:
25.7 Mt @ 1.0% Li2O (at a 0.5% Li2O cut off)
26% of the MRE in higher confidence Indicated category: 6.7Mt @ 1.0 Li2O% as shown in the table below.
Yinnetharra Lithium December 2023
Cut-off
Ta2O5
Li2O
Resource category
Grade
grade
(Li2O%)
Tonnes
(Mt)
Grade
(% Li2O)
Li2O
(Kt)
-
-
-
Total Indicated
6.7
1.0
65
51
Total Inferred
19.0
1.0
181
67
Total Measured
Notes:
(ppm Ta2O5)
Total
25.7
1.0
246
62
Tonnages and grades have been rounded to reflect the relative uncertainty of the estimate. Inconsistencies in
the totals are due to rounding.
Table 1: – Yinnetharra JORC Resource
4
DELTA LITHIUM LIMITED
Interim Financial Report 31 December 2023
•
Drilling results received from the Yinnetharra Lithium Project including:
o 29m @ 1.5% Li2O from 203m Inc. 11m @ 3% Li2O from 221m in YRRD120
o 36m @ 1.1% Li2O from 254m Inc. 6m @ 3.1% Li2O from 282m in YRRD095
o 30m @ 1.1% Li2O from 291m Inc. 10m @ 2.2% Li2O from 310m in YRRD071
o 29m @ 1.0% Li2O from 199m in YRRD133
o 15m @ 1.5% Li2O from 135m in YRRD212
o 68.9m @ 1% Li2O from 128m in YDRD018
o 47.3m @ 1.3% Li2O from 82.6m in YDRD011
o 44m @ 0.84% Li2O from 3m in YDRD249
o 18.5m @ 1.1% Li2O from 64.8m in YDRD014
o 25.5m @ 0.8% Li2O from 38m in YDRD015
o 27.9m @ 1.1% Li2O from 158m in YDRD017
o 21.0m @ 1.2% Li2O from 165m in YRRD260
Figure 2: Plan showing drilling at Malinda.
Work also commenced at the Jameson Prospect prior to the year-end, in preparation for heritage and environmental surveys
which will lead into an enhanced drilling program planned for Q1 of 2024. Once drilling is complete, the team will then
undertake engineering, metallurgical and geotechnical studies for ore analysis and to investigate economic feasibility of the
site.
Mt Ida Project
The Mt Ida Project, located in the Goldfields region of Western Australia, is an advanced, shovel ready lithium mine site with
all environmental and mining permits in place, ready for Open Pit Phase 1 operations. During the most recent half-year, the
team has dedicated their efforts to refining knowledge of the orebody with infill drilling programs in addition to defining an
initial gold resource adjacent to the Sister Sam lithium orebody.
5
DELTA LITHIUM LIMITED
Interim Financial Report 31 December 2023
The granting of Mining Approval for open pit operations during the reporting period now allows the Company to choose when
to proceed. The high-grade shallow gold resources adjacent to the lithium resource could also be mined with minimal
modification to the approved plan. Delta continues to assess opportunities to exploit the gold resources in order to attribute
value for shareholders.
During the half-year, the Board decided that at this stage of the price cycle it is not feasible to commence DSO lithium mining
as previously anticipated. The rapid and pronounced change in the lithium market has forced many industry participants to
adapt their approach and it would be imprudent for Delta to proceed with the prior plans. The Company maintains the
optionality to do so and will continually assess lithium market conditions in this regard.
In October of 2023, the Company completed the infill drilling campaign that lifted the Indicated Mineral Resources by 136% to
7.8Mt @ 1.3% Li2O. The substantial increase in Indicated Mineral Resources strategically positions Delta for detailed feasibility
studies on the primary lithium concentrate project at Mt Ida. Design and engineering studies remain ongoing and the Company
looks forward to reporting on the results of this advanced study. The total Mt Ida Project Mineral Resource was brought up to
14.6Mt @ 1.2% Li2O as a result of the drilling campaign.
The longer-term plan for Mt Ida is to produce a lithium concentrate product with detailed technical work ongoing. The team
is working hard to determine the optimal path forward considering both potential underground and open pit mining to deliver
the best return to shareholders from the identified resources.
Table 2: Mineral Resource Estimate for Mt Ida Lithium Project.
Mt Ida Lithium September 2023
Cut-off
Resource category
Sparrow
Tonnes
Grade
Li2O
Grade
(Li2O%)
(Mt)
(% Li2O)
(Kt)
(Ta2O5 ppm)
Measured
-
-
-
-
Indicated
1.3
1.0
14
189
1.2
0.9
11
144
2.5
1.0
25
167
Inferred
0.55
Measured
-
-
-
-
Indicated
1.5
1.2
18
206
1.3
1.1
14
156
Total Resource
2.7
1.2
32
183
Measured
-
-
-
-
5.0
1.4
72
238
4.3
1.2
50
156
9.3
1.3
123
200
Total Measured
-
-
-
-
Total Indicated
7.8
1.3
104
224
Total Inferred
6.8
1.1
76
154
Total
14.6
1.2
180
191
Inferred
0.55
Indicated
Sister Sam
Ta2O5
grade
Total Resource
Timoni
Li2O
Inferred
Total Resource
0.55
Notes:
Tonnages and grades have been rounded to reflect the relative uncertainty of the estimate. Inconsistencies in the totals are due to rounding.
6
DELTA LITHIUM LIMITED
Interim Financial Report 31 December 2023
In addition to the lithium MRE upgrade, Delta also released a maiden Inferred and Indicated Mineral Resource Estimate for gold
at Mt Ida of 3.1Mt @ 4.1g/t Au for 412,000 ounces. Some notable highlights include:
50% of the gold MRE is in the higher confidence Indicated Resource category
approximately 85% of the gold MRE is co-located adjacent to the defined lithium MRE.
100% of the gold MRE sits within granted Mining Leases
Figure 3: Detailed plan from Mt Ida showing latest results from infill drilling.
7
DELTA LITHIUM LIMITED
Interim Financial Report 31 December 2023
The maiden gold MRE includes two shallow high-grade discoveries, the Baldock 086 lode and the Meteor North 140 lode.
Baldock 086
High-grade shallow gold resource of 0.24Mt @ 9g/t Au for 70koz potentially amenable to open pit mining and in close proximity
to the top of the Sister Sam lithium resource.
Meteor North 140
High-grade shallow gold resource located just north along strike from the Timoni lithium resource of 0.6Mt @ 4.7g/t Au for
91koz, also with potential to mine via open pit.
The proximity of the gold deposit potentially de-risks the development of Mt Ida by generating early cash flow via sale or toll
treatment of high grade, shallow gold resources for minimal incremental cost. The Company is considering multiple options to
realise value from the gold resources at Mt Ida.
Eureka Gold Project
The Eureka gold project is located roughly 50km north of Kalgoorlie. Access is via the Goldfields Highway from Kalgoorlie then
2km unsealed road. Eureka is a high-grade asset on granted Mining Leases with strong potential for walk-up drill targets.
Management consider that the strike and depth potential of the Eureka mineralised system has not been fully tested, and hosts
potential for additional shallow mineralisation in a strongly endowed mineral terrain.
The resource was last updated in June 2021 by CUBE consulting and is tabled below:
Resource Category Cut-off Grade
Indicated
Inferred
ALL Resources
Tonnes
Grade
Contained Metal
(t)
(g/t Au)
(Oz Au)
0.3
1,437,000
1.4
65,000
0.5
1,269,000
1.5
62,000
0.8
983,000
1.8
56,000
1.0
811,000
2.0
52,000
0.3
1,341,000
1.2
52,000
0.5
1,183,000
1.3
50,000
0.8
887,000
1.5
43,000
1.0
666,000
1.7
37,000
0.3
2,778,000
1.3
116,000
0.5
2,452,000
1.4
112,000
0.8
1,870,000
1.7
100,000
1.0
1,477,000
1.9
88,000
Table 3: Eureka Gold Project– In Situ Mineral Resources (as of 23 June 2021).
Earaheedy Basin project
The Company relinquished its land position in the Earaheedy Basin during the half-year ended 31 December 2023.
Corporate
Accelerated Non-Renounceable Entitlement Offer
Delta raised approximately $70.2 million via an accelerated non-renounceable entitlement offer in November of 2023. Proceeds
from the Entitlement Offer ensures that the Company is:
•
•
Well-funded for expanded drilling programs at both the Mt Ida Lithium Project in the Goldfields region, and the
Yinnetharra Lithium Project in the Gascoyne region, of Western Australia; and
Fully funded through to the delivery of a scoping study at Yinnetharra as well as a Definitive Feasibility Study and a
Final Investment Decision at Mt Ida, expected in late-2024.
8
DELTA LITHIUM LIMITED
Interim Financial Report 31 December 2023
Binding agreement with Dalaroo Metals Ltd
In December of 2023, the Company entered a Binding agreement with Dalaroo Metals Ltd (ASX: DAL) to purchase the LCT
(lithium, caesium and tantalum) Mineral Rights over its Lyons River Project in the Gascoyne region of Western Australia.
The Lyons River Project tenements cover 838 km2 and is located to the southwest of Delta’s existing Yinnetharra Project. The
geology contains similar granite intrusives and sediment-mafic packages that host the significant Li2O mineralisation at
Yinnetharra. As a result of this transaction, Delta’s lithium footprint in the emerging Gascoyne lithium province has increased
by 161% to 1,356 km2. These tenements have previously shown early encouraging signs with mapped pegmatite swarms and
lithium in soil anomalies up to 334 ppm Li2O.
Early exploration activities are planned for the DAL tenure alongside continued exploration at Yinnetharra in the first quarter
of 2024.
Board and Management
On 2 August 2023, Delta appointed Mr Steven Kovac as Non-Executive Director.
On 12 September 2023, Delta appointed Mr Chris Ellison as Non-Executive Chairman and Mr Joshua Thurlow as Non-Executive
Director. Mr Ellison is the founder and Managing Director of Mineral Resources Limited who has a shareholding of 23.10%.
With the appointment of Mr Ellison and Mr Thurlow, the Board resolved to remove the role of Executive Chairman and David
Flanagan left the Company. Mr James Croser was appointed to the position of Managing Director and CEO and continues in that
role.
Chris Ellison, Non-Executive Chairman
Mr Ellison is the Managing Director of Mineral Resources Limited. Mr Ellison is the founding shareholder of each of the three
original subsidiary companies of Mineral Resources (Crushing Services International Pty Ltd, PIHA Pty Ltd and Process Minerals
International Pty Ltd). He has more than 40 years of experience in the mining contracting, engineering and resource processing
industries.
Joshua Thurlow, Non-Executive Director
Mr Thurlow is the current Chief Executive – Lithium for Mineral Resources Limited and is responsible for the continued growth
of the MinRes lithium assets and partnerships. He has more than 20 years’ experience in the mining and resources sectors across
Asia Pacific, Africa and North America. Joshua’s expertise spans corporate strategy, social responsibility, business development
and growth, and operations leadership. Joshua is a qualified mining engineer and holds a Master of Business Administration.
Steven Kovac, Non-Executive Director
Mr Steven Kovac, is the current Chief Executive Officer of Idemitsu Australia. Mr Kovac holds a Bachelor of Engineering (Mining),
an MBA and is a Graduate of the Australian Institute of Company Directors. Over his 23-year career in the mining sector he has
had extensive technical and operational experience at a site level, holding senior management and executive level roles for
the past 14 years.
Mr Kovac is also a Non-Executive Director of Critical Minerals Group Ltd (ASX:CMG), a Non-Executive Director of Vecco Group
Pty Ltd, an alternate Director of Low Emission Technology Australia and an Executive Committee member of New South
Wales Minerals Council. He is a member of the Australian Institute of Mining and Metallurgy and the Mine Managers
Association of Australia.
Competent Persons Statement
Information in this Announcement that relates to exploration results is based upon work undertaken by Mr. Charles Hughes,
a Competent Person who is a Member of the Australasian Institute of Mining and Metallurgy (AUSIMM). Mr. Hughes has
sufficient experience that is relevant to the style of mineralisation and type of deposit under consideration and to the activity
which he is undertaking to qualify as a ‘Competent Person’ as defined in the 2012 Edition of the ‘Australasian Code for
Reporting of Exploration Results, Mineral Resources and Ore Reserves’ (JORC Code). Mr. Hughes is an employee of Delta
Lithium Limited and consents to the inclusion in this announcement of the matters based on his information in the form and
context in which it appears. Refer to www.deltalithium.com.au for past ASX announcements.
Past Exploration results and Mineral Resource Estimates reported in this announcement have been previously prepared and
disclosed by Delta in accordance with JORC 2012. The Company confirms that it is not aware of any new information or data
that materially affects the information included in these market announcements. The Company confirms that the form and
content in which the Competent Person's findings are presented here have not been materially modified from the original
market announcement, and all material assumptions and technical parameters underpinning Mineral Resource Estimates in
the relevant market announcement continue to apply and have not materially changed. Refer to www.deltalithium.com.au
for details on past exploration results and Mineral Resource Estimates.
9
DELTA LITHIUM LIMITED
Interim Financial Report 31 December 2023
Forward looking statements
This document may contain “forward-looking statements” and other forward-looking information based on the Group’s
expectations, estimates and projections as of the date on which the statements were made. This forward-looking information
includes, among other things, statements with respect to the Group’s business strategy, plan, development, objectives,
performance, outlook, growth, cash flow, projections, targets and expectations, Mineral Resources and results of exploration.
Generally, this forward-looking information can be identified by the use of forward-looking terminology such as ‘outlook’,
‘anticipate’, ‘project’, ‘target’, ‘likely’,’ believe’, ’estimate’, ‘expect’, ’intend’, ’may’, ’would’, ’could’,’ should’,
’scheduled’, ’will’, ’plan’, ’forecast’, ’evolve’ and similar expressions. Persons reading this document are cautioned that such
statements are only predictions, and that the Group’s actual future results or performance may be materially different.
Forward-looking information is subject to known and unknown risks, uncertainties and other factors that may cause the
Group’s actual results, level of activity, performance or achievements to be materially different from those expressed or
implied by such forward-looking information. Forward-looking information is developed based on assumptions about such
risks, uncertainties and other factors, including but not limited to general business, economic, competitive, political and
social uncertainties; the actual results of current exploration activities; conclusions of economic evaluations; changes in
project parameters as plans continue to be refined; future commodity prices; possible variations of ore grade or recovery
rates; failure of plant, equipment or processes to operate as anticipated; accident, labour disputes and other risks of the
mining industry; and delays in obtaining governmental approvals or financing or in the completion of development or
construction activities. This list is not exhaustive of the factors that may affect our forward-looking information. These and
other factors should be considered carefully and readers should not place reliance on such forward-looking information.
Recipients of this document must make their own investigations and inquiries regarding all assumptions, risks, uncertainties
and contingencies which may affect the future operations of the Group and the Group’s securities. The Group disclaims any
intent or obligations to or revise any forward-looking statements whether as a result of new information, estimates, or
options, future events or results or otherwise, unless required to do so by law.
CONVERTIBLE SECURITIES
Options
At the date of this report, unissued shares of the Group under option are:
Number of Securities
Exercise Price
2,666,666
$0.75
Number Vested &
Exercisable
2,666,666
5,186,293
$0.25
5,186,293
01 Oct 2024
8,048,817
$0.25
8,048,817
18 Nov 2024
1,000,000
$0.77
1,000,000
26 Jul 2025
3,000,000
$0.25
3,000,000
21 Sep 2025
5,000,000
$0.85
5,000,000
30 Sep 2025
24,901,776
Expiry Date
27 Mar 2024
24,901,776
Performance Rights
At the date of this report, unissued shares of the Group pursuant to performance rights issued to incentivise its directors,
employees and other vendors are:
Number of Securities
Grant Date
2,700,000
16-Jan-23
Number Vested &
Exercisable
800,000
1,500,000
8-May-23
-
1,250,000
13-Jun-23
500,000
13-Jun-28
787,500
16-Aug-23
262,500
16-Aug-28
300,000
4-Sep-23
100,000
4-Sep-28
6,537,500
1,662,500
10
Expiry Date
23-Jan-28
8-May-28
DELTA LITHIUM LIMITED
Interim Financial Report 31 December 2023
FINANCIAL REVIEW
Losses from ordinary activities after income tax
Cents per share for losses attributable to the ordinary equity holders of the company
31-Dec-23
$
(1,685,170)
(0.31)
31-Dec-22
$
(2,794,368)
(0.85)
The Company had cash and cash equivalents of $116,310,970 on hand as at 31 December 2023 (30 June 2023: $84,311,712).
SUBSEQUENT EVENTS
On 2 January 2024, the Company elected to pay the deferred consideration in relation to the acquisition of the issued capital
in Electrostate Limited (owner of the Yinnetharra Lithium Project) by issue of 21,720,247 ordinary shares at a price if $0.46
per share (refer note 12).
On 9 March 2024, the Company entered into an agreement with Voltaic Strategic Resources (VSR) to acquire an interest
in the Ti Tree project. Key terms of the transaction are:
•
Upfront consideration of $1.25 million.
•
Commitments of $3 million in exploration expenditure (minimum spend of $1 million) through stage 1 to earn in
51% interest with a payment of $0.5 million to VSR at completion of stage 1.
•
Commitments of a further $6.25 million (for a total of $ 9.25 million) of exploration expenditure to stage 2 to
earn in 80% with a payment of $1 million to VSR at completion of stage 2.
On 9 March 2024, the Company entered into an agreement with Reach Resources to acquire an interest in the Morrissey
Hill and Camel Hill projects. Key terms of the transaction are:
•
Upfront consideration of $3.2 million.
•
Commitments of $3 million in exploration expenditure through stage 1 to earn in 51% interest.
•
Commitments of a further $6 million (for a total of $9 million) of exploration expenditure to stage 2 to earn in
80%.
•
Payments of approximately $10 million upon definition of a resource of greater than 7.5Mt.
For further details on the above agreements, refer to ASX announcement dated 11 March 2024.
There were no other subsequent events that required adjustment to or disclosure in the interim financial report.
AUDITORS’ INDEPENDENCE DECLARATION
A copy of the auditor’s independence declaration as required under section 307C of the Corporations Act 2001 is set out on
page 12.
This report is signed in accordance with a resolution of the Board of Directors.
James Croser
Managing Director
Dated 12 March 2024
11
Lead Auditor’s Independence Declaration under
Section 307C of the Corporations Act 2001
To the Directors of Delta Lithium Limited
I declare that, to the best of my knowledge and belief, in relation to the review of Delta Lithium Limited
for the half-year ended 31 December 2023 there have been:
KPMG
i.
no contraventions of the auditor independence requirements as set out in the Corporations
Act 2001 in relation to the review; and
ii.
no contraventions of any applicable code of professional conduct in relation to the review.
Glenn Brooks
Partner
Perth
12 March 2024
KPMG, an Australian partnership and a member firm of the KPMG global organisation of independent member firms affiliated
with KPMG International Limited, a private English company limited by guarantee. All rights reserved. The KPMG name and
logo are trademarks used under license by the independent member firms of the KPMG global organisation. Liability limited
by a scheme approved under Professional Standards Legislation.
DELTA LITHIUM LIMITED
Interim Financial Report 31 December 2023
Condensed Consolidated Statement of Profit or Loss and Other Comprehensive Income
For the half-year ended 31 December 2023
31-Dec-23
31-Dec-22
$
$
1,250,281
141,124
-
(40,167)
1,250,281
100,957
Employee benefits expense
(2,490,288)
(757,384)
Corporate & administrative expenses
(1,438,005)
(788,144)
Public relations & marketing expenses
(384,567)
(252,562)
Notes
Income
Other income
6
Net (loss) on disposal & deconsolidation of subsidiary
Total income
Expenditure
Share-based payments
17
564,268
(1,720,922)
Net fair value gain/(loss) on financial assets
8
(268,040)
35,396
Impairment reversal/(expense)
9
(500,408)
500,000
(124,105)
(53,350)
Total expenditure
(4,641,145)
(3,036,966)
Operating loss
(3,390,864)
(2,936,009)
Finance income
1,781,572
187,041
Finance costs
(75,878)
(45,400)
1,705,694
141,641
(1,685,170)
(2,794,368)
-
-
(1,685,170)
(2,794,368)
-
38,590
Other comprehensive income / (loss) net of tax for the year
(1,685,170)
(2,755,778)
Total comprehensive loss for the year is attributable to owners of the company
(1,685,170)
(2,755,778)
Loss per share
Basic and diluted loss for the year attributable to ordinary equity holders
of the parent (cents per share)
(0.31)
(0.85)
Loss per share for continuing operations
Basic and diluted loss for the year attributable to ordinary equity holders
of the parent (cents per share)
(0.31)
(0.85)
Depreciation
Net finance income
Loss before income tax from continuing operations
Income tax expense
Loss after income tax from continuing operations
Items that may be reclassified subsequently to profit and loss
Reclassification of foreign currency differences on disposal of subsidiary
The above condensed consolidated statement of profit or loss and other comprehensive income should be read in conjunction
with the accompanying notes.
13
DELTA LITHIUM LIMITED
Interim Financial Report 31 December 2023
Condensed Consolidated Statement of Financial Position
As at 31 December 2023
31-Dec-23
30-Jun-23
$
$
116,310,970
84,311,712
2,031,293
2,429,298
1,270,717
1,538,757
119,612,980
88,279,767
138,868,688
105,016,898
2,671,887
1,211,486
764,027
111,389
Total non-current assets
142,304,602
106,339,773
Total assets
261,917,582
194,619,540
Notes
Current assets
Cash and cash equivalents
7
Trade and other receivables
Financial assets at fair value through profit or loss
8
Total current assets
Non-current assets
Exploration and evaluation expenditure
9
Plant and Equipment
Right-of-Use Asset
10
Current liabilities
Trade and other payables
11
6,862,118
7,777,053
Lease Liability
10
175,877
90,874
Deferred Consideration
12
10,000,000
10,000,000
17,037,995
17,867,927
Total current liabilities
Non-current liabilities
Provision - rehabilitation
13
2,256,591
2,389,779
Lease Liability
10
598,058
26,686
Total non-current liabilities
2,854,649
2,416,465
Total liabilities
19,892,644
20,284,392
Net assets
242,024,938
174,335,148
Equity
Share capital
14
258,905,692
188,810,114
Share-based payment reserve
15
9,313,697
10,034,315
Accumulated losses
16
(26,194,451)
(24,509,281)
242,024,938
174,335,148
Total Equity
The above condensed consolidated statement of financial position should